SAFETY, INSTALLATION & OPERATION MANUAL
SAFETY,
INSTALLATION & OPERATION MANUAL
FOR
Chapter 1 DESCRIPTION OF ABSORPTION CHILLER
1.1 Description of Formation of Type Number
□
-----□ □
Design number: H2
(H2-type Unit)
Nominal cooling
capacity: (USRT)
Chiller type: SS-steam
operated single effect lithium bromide absorption chiller
Type Example:
SS-331H2 will be the H2
type steam operated single effect lithium bromide absorption chiller with steam
pressure 0.1MPa(G), cooling capacity 331USRT, chilled water inlet/outlet
temperature 12/7°C and MMI2 control.
1.2 The Nominal Operation Conditions and Working Limits
For the nominal operation conditions of
chiller, see data on the nameplate.
Allowed working limits:
Chilled water outlet temperature (t): Nominal value minus 2°C£ t £ Nominal value plus 3°C Cooling water inlet
temperature (t): 18°C£ t £ 34°C
Nominal working steam pressure: Not more than nominal
working steam pressure plus 0.05MPa
1.3 Configuration of Chiller
H2 type Steam-operated single effect lithium
bromide absorption chiller (shortened as chiller hereinafter) is a equipment,
which uses saturated steam as heat source, water as refrigerant, lithium
bromide as absorbent, produces the chilled water under vacuum conditions for
the purpose of air-conditioning and technology process.
The chiller consists of following main
parts: generator, condenser, evaporator, absorber, heat exchangers; and such
auxiliary parts as purging unit, de-crystallization piping and
hermetically-sealed pumps (solution pump and refrigerant pump). The external
view of absorption chiller is shown in the Fig. 1-1, 1-2 and 1-3. The valves
for different chillers are listed in Table 1-1.
1.
Gas cylinder
2.
Upper purging valve of vacuum pump
3.
Lower purging valve of vacuum pump
4.
Purging sampling valve
5.
Vacuum pump
6.
Charging valve
7.
Solution valve
8.
Strong solution sampling valve
9.
Refrigerant spray valve
10.
Refrigerant pump
11.
Refrigerant sampling valve
12.
Refrigerant by-pass valve
13.
Control panel
14.
Heat exchanger I
15.
Heat exchanger II
16.
Condensate heat exchanger
17.
De-crystallization pipe
18.
Steam inlet
19.
Condensate outlet
20.
Absorber
21.
Evaporator
22.
Cooling water inlet
23.
Chilled water inlet
24.
Chilled water outlet
25.
Cooling water outlet
26.
Condenser
27.
Generator
|
Fig. 1-1 Front view of chiller
Fig. 1-2 Rear view of chiller
Fig.1-3 Left and right views of chiller
Table 1-1 List of valves on the chiller
No
|
Description
|
Purpose
|
Group
|
Type
|
2
|
Upper
purging valve of vacuum pump
|
For
purging non-condensable gases from chiller, and opened during purging by
vacuum pump. Opened when measuring the internal pressure in the chiller and
leak testing under charged nitrogen in the chiller. NC(Normally closed).
|
Purging
valves
|
Stop
valves
|
3
|
Lower
purging valve of vacuum pump
|
For purging non-condensable gases from
chiller and gas cylinder, open when chiller is running, close when chiller is
stop.
|
||
4
|
Sampling
purging valve
|
For measuring the vacuum pump performance,
and purging the external vessel (such as sampler) by vacuum pump. NC.
|
||
6
|
Charging
valve
|
Used for charging and drain solution from
chiller, and sampling of weak solution. NC.
|
Solution
valves
|
Stop
valves
|
8
|
Strong
solution sampling valve
|
For sampling of strong solution. NC.
|
||
9
|
Refrigerant
spray valve
|
To adjust spraying quantity of refrigerant
water. NO (Normally open).
|
Refrigerant
valve
|
Vacuum
butterfly valve
|
11
|
Refrigerant sampling valve
|
For sampling of refrigerant and charging
and drain refrigerant, and charging gas into the chiller when test the
chiller under positive pressure. NC.
|
Refrigerant
valves
|
Stop
valves
|
12
|
Refrigerant
by-pass valve
|
For regeneration of refrigerant or
dilution solution, by-passing part of refrigerant from evaporator to
absorber. NC.
|
Generator
Generator is the shell and tube structure,
consists of cylinder, heat transfer tubes, thermal insulating layer, solution
baffle and heat transfer tube bundles, etc. The working steam from boiler or
external system flows through the inside of heat transfer tubes and heats LiBr
solution outside of it, then generates high temperature refrigerant vapor.
Meanwhile solution concentrates into strong solution. The working steam
releases heat in the heat transfer tubes and become condensate, then flow into
condensate heat exchanger via condensate solution packing. The pressure of the
steam generator is about 7.9kPa (59mmHg).
Condenser
Condenser consists of cylinder, heat
transfer tubes and end covers. Cooling water from cooling tower (about 32℃), enters heat transfer tube via
end covers, to condense the vapor from generator, then cooling water left the
condenser at temperature about 40℃
to the cooling tower. Produced refrigerant water flows into evaporator through
U pipe throttle. A part of refrigerant water is flashed and cooled, and enters
refrigerant water pan. Condenser and generator are arranged in one shell (upper
shell) with identical pressure.
Evaporator
Evaporator consists of heat transfer tubes,
end covers, and water distribution pan, refrigerant water pan, refrigerant
water chamber and refrigerant pump. Chilled water from customer (about 12℃)
enters heat transfer tubes through end covers, and evaporates refrigerant
water, which is sprayed over the tubes by the refrigerant pump from water
chamber. Rest of water, which had not been evaporated is collected in the water
pan, and is sent to distribution tube again to evaporate. Thus produced chilled
water runs from the evaporator at temperature about 7℃
into the system of customer. Pressure in the evaporator is about 0.9Kpa (6.75
mmHg).
Absorber
Absorber consists of heat transfer tubes,
end covers, water distribution pan, solution chamber and solution pump. Cooling
water from cooling tower (about 32℃) enters the heat
transfer tubes through end covers to cool the strong solution distributed
outside tubes. At a set temperature and concentration (for instance 52℃ and
64%) lithium bromide solution possesses tremendous water vapor absorbing
capacity, and absorbs considerable refrigerant vapor, produced in the
evaporator in the same shell, and transfers the heat to the cooling water.
After absorbing water vapor, solution is diluted, and flows into the lower
solution chamber, then sent to generator to be concentrated. Absorber and
evaporator locate in the same shell under the identical pressure. Absorber is
divided into two parts, which are arranged in both sides of evaporator.
Solution heat exchanger
Solution
heat exchanger consists of two heat exchangers, which are composed of heat
transfer tubes, supporting rods, front and rear end covers and headers. Weak
solution flows through internal part of tubes, and strong solution pass over
the tubes. Heat exchanger has the purpose of increasing the temperature of weak
solution and reducing that of strong solution.
Condensate heat exchanger
Condensate
heat exchanger consists of heat transfer tubes, supporting rods, front and
rear end covers. Weak solution passes over the tubes and steam condensate flows
through internal part of tubes. Heat exchanger has the purpose to make weak
solution absorb heat of steam condensate and increase its temperature.
Purge unit
Purge
unit consists of purge piping (arranged in absorber and condenser) and gas
box, ejector, gas cylinder, solution return pipe, stop valves, and vacuum pump.
It is functioned for purge non-condensable gas from the chiller/heater to
reduce the influence of gas to the normal operation of chiller. During its
operation, the non-condensable gas is extracted through purge piping to the
pressure reduced area of ejector, which is created by a part of weak solution,
supplied by the solution pump from absorber. Then gas flows with solution into
the gas cylinder. Gas is stored in the gas cylinder and gas box, and solution
returns into the absorber through solution return pipe. Stored gas can be
discharged into atmosphere by vacuum pump manually or automatically, if
pressure reaches setting value.
De-crystallization pipe
De-crystallization pipe: Mounted between generator and absorber, a
channel for strong solution in solution heat exchanger returning to absorber
directly after decrystallization. When solution heat exchanger gets
crystallized, strong solution that should have went to absorber from heat
exchanger can’t go for blocking, which would result in strong solution level in
generator going up gradually until it’s falling down to the absorber directly
through decrystallization pipe. Strong solution of high temperature which is
not reducing temperature will be mixing with weak solution in absorber to make
the temperature of the mix going up; the heat accumulated gradually will be
used for dissolving the crystallization.
Hermetically-sealed pumps
Hermetically-sealed pumps (solution pump and refrigerant pump) are
used to handling the working media in the chiller/heater. Solution pump has the
purpose to send the lithium bromide weak solution from absorber to generator
through heat exchanger. Concentrated strong solution in generator is returned
to absorber. Refrigerant pump is used to spray refrigerant over the tubes in
the evaporator by extracting refrigerant from refrigerant pan of evaporator,
then refrigerant is evaporated by heat of chilled water.
Control panel
Control
panel is the control center of chiller/heater. For details of control
panel, see Chapter 4.
1.4 Working Fluid
1.4.1
Refrigerant
As the refrigerant of absorption chiller,
water is used. For producing chilled water with 7℃ , pressure in the evaporator is
only 0.9kPa (6.78 mmHg), and saturation temperature under such pressure is 5.5℃,
which is the boiling point of water under such conditions. Refrigerant water is
handled from the refrigerant pan of evaporator, and sprayed over the tubes in
the evaporator. System water is chilled in the evaporator, which gives heat to
refrigerant, and decreases temperature. In the mean time, the refrigerant water
gains heat and evaporates to be refrigerant vapor.
1.4.2
Absorbent
As absorbent for the chiller, lithium
bromide solution is used. It can be taken as the carrier of refrigerant water,
and functions as to absorb the refrigerant vapor, produced in the evaporator by
removing heat of chilled water, and carries refrigerant into generator. Weak
solution is divided into strong solution and refrigerant vapor under the heat
of supplied steam. Separated refrigerant vapor enters condenser to be condensed
by dissipating the heat into atmosphere through cooling water. Refrigerant
condensate returns into evaporator to produce cooling effect, and heat is taken
away by cooling water.
The new charged solution should meet the
following technical requirements:
Item
|
M-Series LiBr solution with Lithium Molybdate
inhibitor
|
C-Series LiBr solution with
Lithium Chromate inhibitor
|
Color
|
Colorless
|
Yellow
|
LiBr
|
(50.0±0.5)%
|
(50.0±0.5)%
|
LiOH
|
0.06~0.07 N
|
--
|
PH value
|
--
|
9.0~10.5
|
Li2MoO4
|
0.005%~0.030%
|
--
|
Li2CrO4
|
--
|
0.15%~0.25%
|
Quality of lithium bromide solution influences
the performance of chiller directly, so the solution, produced by the Company,
must be used.
Solution in the chiller held in
predetermined limits of concentration. Too high concentration and too low
temperature can lead to separation of crystals from solution, known as
crystallization. Severe crystallization will prevent chiller from normal
operation. Solubility curve for LiBr solution can see attachment 1.
LiBr solution corrodes
metal material, especially in the presence of oxygen. Corrosion takes place
very quickly, and shortens the operation life of chiller, so the chiller should
be kept under high vacuum conditions. In addition, proper content of lithium
chromate in solution and maintaining pH within 9.0~10.5 are also essential to
corrosion prevention. Measures should be taken in accordance with the
recommendations, contained in the following text, when the content of lithium
chromate and pH values are not in the specified limits.
LiBr solution without
addition of corrosion-inhibitor is a colorless, transparent and nonpoisonous
liquid. With the addition of Li2MoO4, it is changed to colorless,
and nontoxic. With the addition of Li2CrO4, it is changed
to light yellow, and slightly poisonous. Skin spattered with LiBr solution is
itching. Make sure that LiBr solution does not directly contact with skin. Wash spattered skin with
clean water.
1.5 Working Process
Working process is shown in the Fig. 1-4.
The chiller is purged from non-condensable gases, and kept under high vacuum
conditions.
Fig. 1-4 Flow chart of chiller with control point
Weak solution from the absorber is pumped
into the generator through heat exchanger and condensate heat exchange. It is
heated by operating steam and concentrated to the strong solution, and high
temperature refrigerant vapor is produced. Strong solution enters generator
through heat exchanger in exchanging heat with weak solution which is passed
through the tubes, and returns to absorber after cooled. Refrigerant vapor from
generator enters condenser, and is condensed into refrigerant water by cooling
water in condenser tubes and heat is taken away by refrigerant water. The
refrigerant water flows into evaporator through U pipe and is flashed and
enters evaporator refrigerant pan. Refrigerant from evaporator refrigerant pan
is pumped over the evaporator tubes for the refrigeration effect, and
evaporates to form vapor by absorbing heat of chilled water flowing through
tubes. Produced refrigerant vapor enters absorber, and absorbed by strong
solution in the absorber. Chilled water is cooled and returns to the system of
customer. Strong solution is diluted by absorbing refrigerant vapor , then is
transferred by solution pump to generator for concentration. Heat generated is
carried to atmosphere by cooling water. This process is continued, and
refrigeration effect is repeated.
1.6 Performance of Chiller
The chiller will operated under changed
external conditions (such as air conditioning load, cooling water
temperature). The chiller performance
under changed conditions are shown in Fig.1-5, 1-6, 1-7. These performance
curves are given for customer’s reference, and the working conditions cannot be
outside the limits given.
Conditions:
Working steam
pressure: the nominal value
Chilled water flow 100%
Cooling water flow
100%
Scale coefficient 0.086 m2.K/kW
|
Fig.1-5
Relation of cooling capacity to chilled water
outlet
temperature and cooling water inlet temperature
Fig.1-6
Relation of cooling capacity to steam consumption
Conditions:
Working steam pressure:
the nominal value
Chilled water outlet
temperature 7℃
Chilled water flow
100%
Cooling water inlet
temperature 32℃
Scale coefficient 0.086 m2.K/kW
|
Fig.1-7
Relation of cooling capacity to
cooling water flow
Chapter 2 INSTALLATION OF CHILLER
2.1 Requirements to Maintenance during Installation
For chiller tested in the Company, customer
should pay attention to check the chiller for its air tightness with our
service engineers.
During storage and installation of chiller,
customer is required to observe the vacuum conditions of chiller in accordance
with the provisions of paragraph 5.1.4. Observe the vacuum conditions daily.
Information about the change of reading of pressure gauge should be given to
the service engineer of Company. Abnormality of chiller, observed by the
service engineer of Company, should be corrected by the customer under his
guidance and technical manual.
Air leaks in the chiller,
causes corrosion of internal parts, affects its operation life, and prevents it
from normal operation under severe conditions.
During shipping, handling and installation,
chiller should be protected from man-made damage and unauthorized operation of
valves and instruments. In order to protect the chiller from leaks, the
personnel is forbidden to climb the chiller by the piping and valves. Control
panel, electric instrument and wiring should be protected from damage, control
panel is not allowed be opened and wiring be removed by uncertified operator.
Protection means from dampness and rain should be adopted.
All the outlet openings of chiller should be
covered to protect it from ingression of dirty and foreign matter.
With original openings covered and
protections provided, chiller should be covered by a tarpaulin, but not plastic
sheeting (which will permeate damp and speed up its corrosion), when it is left
in the open air. Chiller or its parts, stored for long time in the room or in
the open air, should be covered carefully.
Box with bulk of parts is recommended to
store at dry and safe place to ensure its intact.
2.2 Requirements to Machine Room
1. Machine
room should be designed with good ventilation and lighting facility.
2. Temperature
in the room should be kept in the limits of 5-40℃, and humidity less than 90%.
3. Machine
room should be supplied with power voltage of 380VAC±10%, and without accidental
failure of power.
4. Machine
room is provided with perfect drain system. Machine room should be constructed
against fire and water flood.
5. Machine
room should be arranged in such a way, that the chiller is accessible to
handling, install, maintain, repair, replace the parts and modernize chiller.
Space and height should be reserved for handling and transport the chiller.
6. Minimum
space with the dimensions shown in the Table2-1 should be reserved. Space for
changing tubes (a little smaller than length of chiller) should be provided in
axial direction from any one side of chiller. Chiller can be installed with the
ends against window or door for pulling the leaking tubes.
7. Machine
room should be designed with due considerations of its vibration and noise to
the surrounding rooms, and provided with good sound isolation, attenuation and
vibration absorbing means.
8. Machine
room should be able to carry the total weight of whole package of chiller and
its auxiliary equipment during their operation.
9. Machine
room should be equipped with locks and screens for doors and windows to protect
from the entrance of unauthorized people.
10.
Machine room should be provided with tools, spare parts
and materials for maintenance of chiller and systems.
Axial direction
|
1.0m
|
Above chiller
|
0.2m
|
From control panel
|
1.2m
|
Rear side
|
0.8m
|
2.3 Installation of Chiller
The foundation for chiller should be
designed to carry the chiller with operation weight. as static load, because of
its stable operation and minor vibration. The foundation should be raised from
the floor with dimensions in accordance with installation drawings provided by
our Company. The installation work of chiller is essential to its successful
operation, especially the levelness should be ensured, which is a key link to
ensure performance and normal operation, though the installation of chiller is
not so complicated.
In general, the chiller is installed in the
machine room, but it can be installed outside, if the conditions not allowed.
But, the unit cannot be installed in the open air, when the lowest circumstance
temperature in the year is less than 5℃.When installed outside the room,
means should be taken to protect the chiller body, control panel, measuring and
control instrument, steam adjusting valve and piping valves from rain, wind,
corrosion and heat dissipation.
Chiller should be installed with
consideration of daily operation, and provision of space for withdraws of heat
transfer tubes from any end of chiller. In the mean time, it can be installed
with one end oriented to the window. Drainage should be provided around the
chiller and covered with perforated plate made from cast iron.
Before positioning the chiller on the
fundament, which should be cleaned from dirty, it should be kept level and with
dimensions in accordance with the design requirements. On the support area of
fundament, hard rubber plates with area bigger than supporting foot and
thickness of about 10mm should be covered.
2.3.1
Installation
Of Assembled Chiller
During installation of chiller, it should be
handled carefully with steel ropes placed on the marked area. Every steel rope should
have capacity to carry whole weight of chiller. Chiller should be handled with
care to be protected from damage of any parts. The position of contact of ropes
with the chiller should be adjusted to avoid the damage of parts, such as small
diameter pipes, connecting wires and instrument. Chiller should be handled in
horizontal position with slow movement in order to be protected from drop of
unit owing to deviation of center of gravity, when solution in chiller is
moved. Chiller should be lowered with all feet contacted with the surface of
floor or fundament.
When chiller rolls on steel pipes, distance between two pipes is less
than 0.5m.
To avoid damage of chiller, handling equipment and steel wire should
have capacity to carry weight more than that of chiller. During operation
personnel is not allowed to stay under the handling equipment for avoiding
injuries and deaths.
After positioning of chiller on the
fundament, the longitudinal and transversal levelness should be checked. Two
holes on the both sides of tube plates of evaporator-absorber are provided, and
should be on the same level with deviation less than 1/1000. Chiller can be
raised at one end by crane or two jacks at each side of unit, and long steel
spacer can be inserted between the foot and fundament, or channel steel can be welded at the bottom
of one base, and lift chiller with two lifting jacks to adjust levelness, if
the levelness of unit is not in the prescribed limits.
Deviation from prescribed levelness of installed chiller causes
re-distribution of working fluid flow in the unit, and affects its normal
operation under severe conditions.
2.
3.2 Installation of unit of chiller from split parts
Separation of chiller into split units
impairs vacuum of chiller, and causes its corrosion. Chiller tested in the
works, should not be separated into split parts.
For split chiller, its installation is
basically the same as for assembled unit of chiller. The main difference is:
the separated parts should be put at their own fundament, lined up for
connections, checked for longitudinal and transversal levelness, and welded
together, if it is separated into two parts. Or the lower shell should be put
on the fundament, checked with longitudinal and transversal levelness; then the
upper shell should be put on the lower shell, lined up for connection, checked
for longitudinal and transversal levelness, and welded together with lower
shell. Cautions should be taken to prevent the welding from ingression of slag
and scales into the unit. Welded chiller should be checked again for levelness.
Installed unit should be evacuated, and checked for air tightness.
2.4 Adjustment of Levelness of Chiller
Method of checking the levelness of unit
usually is done by level or with transparent plastic hose and water as follows:
1.
As shown in the Figure 2-1, transparent plastic
hose is hanged close to the level reference holes, and charged with water. The
hose should be without knot and air bubble inside it, and cannot be flattened.
2.
Water lever in one end of hose is kept to the
center of one reference hole. Water level in the another end of plastic hose
should be at same height with the center of another reference hole, adjusting
the height of chiller at another end by crane or other means. The longitudinal
levelness of installed chiller equals to the difference of water level in two
ends divided by the distance between the tube plates. Chiller is kept in the
limits of levelness, which should be less than 1/1000, by insertion of long
steel spacer at the lower end.
3.
The transverse levelness is adjusted in the same
manner by placing the plastic hose along the tube plate.
2.5 Insulation of Chiller
When
the chiller is installed and checked for air tightness, the following parts
should be insulated:
Thermal
insulation locations (~90℃):
generator, heat exchanger, condensate heat exchanger , and hoses connecting
them.
Cold
insulation locations(~7℃):
evaporator water pan, evaporator water chamber end covers, piping before and
after refrigerant pump.
Thickness
of thermal insulation layer: 40mm.
Thermal
insulating material: rock wool felt, super-fine glass fiber felt, or material
with similar property.
Thickness
of cold insulation layer: 30mm.
Cold
insulating material: polyethylene foam plastics, or material with similar
property. Cold insulating material shall not absorb water, and no gas can be
pass through. Joints shall be sealed by adhesive tapes.
Thermal/cold
insulation construction: welding shall not be conducted on the chiller,
electric circuits shall not be damaged and temperature-measuring tubes, valves,
drainage cocks and testing components of control system shall not be covered.
Insulation parts are shown in Fig.2-2.
Fig.2-2 The parts of chiller to be
insulated
Chapter 3 INSTALLATION OF EXTERNAL SYSTEMS
Chiller is provided with external systems, such as water
system (including chilled and cooling water), working steam and condensate
system and electric system, see Fig.3-1.
Fig 3-1 Diagram for external systems
3.1(Chilled and Cooling)Water System
Water piping is designed to ensure the water speed in the
limits of 1.5-2.5m/s (for nominal water flow, see nameplate). Piping should be
constructed with less turns or round turns. Piping is supported or hanged
carefully to prevent the chiller from the load by piping. Chiller is influenced
in operation life by external load or vibration, or damaged during severe
conditions.
At the inlets and outlets chiller and pumps (including spare
pumps) should be provided with compensators (including rubber compensators,
rubber hoses, metal bellows, and metal hoses).
At the inlets of chiller and pumps the detachable filter
with element of large area of 5-8 meshes/inches should be installed. Piping
should be designed to clean filter and maintain the pumps without interrupting
the operation of chiller.
Detachable filters should be installed at
water pump inlet and chilled water inlet of chiller to protect the heat
transfer tubes from clogging by the foreign matters, to protect the chiller
from degradation of performance and rupture of tubes by freezing.
Chiller and pumps (including spare pumps) should be provided
with pressure gauges (or gauge common for measuring pressure at different
locations by switching from location to location, if it desirable). At the
inlets and outlets of chiller thermometers shall be installed. For water
systems of unit, flow meters with scale covering the nominal water requirements
should be installed in manner accessible for reading and maintenance.
Detachable short pipes of about 800 mm in length should be
installed at chilled water inlet and outlet to remove the end cover of
evaporator and clean heat transfer tubes. At the inlet of chiller the
detachable filter with element of large area of 5-8 meshes should be installed.
Water piping should be provided with drain valve at its lowest point, drain
piping led to channel, and vent at its highest point.
Pressure setting device shall meet the requirements for
constant pressure and water drainage when expansion and water makeup when
leakage, if closed water system is used.
Cooling tower shall conform to the requirements of chiller
in water flow and thermodynamic performance. Cooling tower with water
collecting tank should be selected, if no reservoir is provided for the cooling
water system. Cooling tower shall be installed at place far from source of heat
and dust, especially from chimney, with good ventilation, taking consideration
of noise and water drift. Regulating valve and instantaneous water flow meter
should be installed at the make up and drain piping to keep the quality of
cooling water. Cooling tower should be operated by thermostatic control at the
outlet of cooling water from tower, or fan of tower is connected with the
control system of chiller, and on/off controlled from control panel. Bypass
piping with two-way or three-way valves can be connected between the inlet and
outlet of tower to maintain constant temperature of cooling water, while part
of cooling water is bypassed tower into chiller in case of too low temperature
of cooling water.
Pump can be installed at the outlet of chiller to reduce the
water pressure working on the chiller, when water system is operated under
higher pressure.
Pressure working on the water head of chiller
cannot be above its maximum load carrying capability, otherwise, the chiller
cannot be working normally owing to the deformation of water head.
Water treatment means should be provided to protect heat
transfer tubes from corrosion or scale formation, if water cannot meet the
requirements in quality.
Chiller is supplied with a flow switch, which is installed
in a straight section with length not less than 10 times of pipe diameter
(horizontal or vertical) of chilled water piping from the chiller. For installation
of flow switch a round hole shall be done at the straight pipe (or at upside
for horizontal section). Then the support of flow switch shall be welded to the
hole, and switch is installed with deflector perpendicular to the flow
direction. The direction marked on the meter shall be the same for the
direction of water flow. Switch shall be connected with the control system of
chiller. The length of straight section of pipe shall be at least 5 times of
pipe diameter, as shown in Fig.3-2. It is not allowed to reduce the minimum
settings, as the chiller shipped from works with minimum setting of flow.
The chilled and cooling water piping should be designed and
installed with valves at the piping inlets and outlet from the chiller, and a
piping with a valve bypassing the chiller is provided before the valve to the
inlet of chiller and after the valve from the chiller. In order to flushing the
piping, the valves at the inlets and outlets should be closed and valve on the
bypassing piping opened. After the operation, the inlet and outlet valves
should be opened, and valves on the bypassing piping closed.
The chiller should be drained after it tested hydraulically
(or kept with water, if the commissioning is followed).
The chilled water piping should be insulated, when the
chiller is installed and leak tested.
3.2 Working Steam System
Piping is constructed with less turns or round turns, and
installed in accordance with the respective standards.
Regulating valve should be arranged close to the chiller. A
pressure reducer is to be installed, when the working steam pressure is higher
than that of HP generator. A manual stop valve should be provided on the steam
piping for shut off steam, when accidental event occurs. The manual stop valves
should be installed before and after the pressure reducer and steam adjusting
valve, while the bypass piping is provided to inspect and repair the reducer
and regulating valves. Steam over heat is not more than 15℃.
If steam over heat is more
than 15℃, it will cause serious
results, such as chiller’s damage, even generator’s write-off and personal
injury, etc.
A steam/water separator should be installed, if the dryness
of steam is less than 0.99. A drain valve is installed on the lowest point of
piping before the steam entering the chiller. To protect the chiller from
hydraulic hammer, before starting the chiller, the drain valve should be opened
to flush condensate.
The chiller is thermally insulated, when it is mounted,
ensuring no slackness, danger and leakage will take place.
3.3 System of Condensate of Working Steam
The piping of condensate of working steam should be laid
down lower than the HP generator of chiller. If it is installed higher than the
HP generator, then the calculation of condensate pressure, supplied by our
company should be taken into consideration, and measures should be provided to
prevent the back flow of condensate into tube bundles of HP generator, when the
chiller is operated under low load. Drain valve is provided at the lowest point
of condensate piping to avoid the hydraulic hammer in the starting stage.
A condensate tank with highest water level lower than HP
generator is installed after the condensate discharge piping, when condensate
is returned to the boiler house.
System must be cleaned before
it is connected to the chiller unit .otherwise chiller tube will get clogged due
to the deposit in the water/steam , which will lead to chiller performance drop
and serious troubles such as tube frozen .
3.4 Electric System
As power source the three phases and five lines electric
system of AC 380 is used. Power lines are laid to the control panel of chiller
by customer, and connected by Shuangliang engineer during commissioning (Phase
and zero lines are connected to internal terminals in the control panel, and
ground line is connected to the ground screw in the panel). Power lines should
meet the power specifications, indicated on the nameplate of chiller.
Special grounding pole with resistance less than 10Ωshould
be provided, and connected with the grounding line of chiller to ensure the its
safe operation.
Failure of special grounding
pole or using zero line instead of grounding pole will cause severe damage of
chiller or injury or death of personnel.
The standard supplied chiller/heater is provided with
interlocked control of cooling water pump, chilled water pump (including
standby ones) and fans for cooling tower so that the pumps (including standby
ones) and fans for cooling tower will be started/stopped by the control system
of chiller/heater. If more than one chiller/heaters share one cooling water
system, electric driven valves must be set at cooling water inlets of each
chiller/heater to realize interlocked function of control system. The electric distribution
panel should have terminals for connecting control lines for pumps and fans.
The control lines should be laid and marked by customer. For a chiller, 12
control lines of 0.75mm2 should be provided. Power lines should be
laid separately from control ones.
The cooling water pump and chilled water pump should be
working interlocked, i.e. the cooling water pump stop first, and then the
chilled water pump, if no provisions for interlocked controls are used.
Chilled water and cooling
water pumps (including standby ones) and fans for cooling tower must be
interlocked with control system of chiller/heaters. At cooling water inlets of
each chiller/heater, electric driven valves must be set to interlock with
control system, if there are limiting conditions. Otherwise, Shuangliang will
not take any responsibility for malfunction and other bad results such as
rupture of tubes.
For chillers with functions of remote start, stop and
monitoring, the installation of chiller will be proceeded in accordance with the
“The instruction of installation and operation of remote start, stop and
monitoring system”.
4.1 Configuration of System
Advanced control system MMI2 with color touch screen as
man-machine interface is used, and such measuring and control elements, as PLC
controller, platinum resistance, flow switch, pressure sensors, level
controller are implemented to ensure the optimized control of chiller. The
configuration of control system is shown in Fig.4-1.
4.2 Function of System
The control system is used in two modes: automatic and
manual control. Automatic control mode is preferred, manual control is used
only for commissioning and to shooting the failure of chiller.
Control system is designed for efficient and automatic
control of chiller. It is provided with the functions: setting the data,
automatic staring up and shut-down the unit, limit control of cooling water
inlet temperature, limit control of solution concentration, automatic control
of loads and circulating flow of solution, measuring and displaying the
operation data in real time, safety protection, memory and storage of data and
etc.
4.2.1
Normal
functions
No.
|
Name of function
|
Description of function
|
1
|
Data setting
|
For working the chiller
under expected or optimum conditions, the data, including the chilled water
outlet temperature, are set by certified personnel in accordance with the
local conditions.
|
2
|
Automatic start and
stop of chiller
|
Chiller is
started/stopped merely by personnel pressing the touch screen, and will be
operated steadily in nominal conditions.
|
3
|
Limit control of cooling
water inlet temperature (cooling mode)
|
Chiller will be
operated steadily by limiting its capacity under low inlet temperature of
cooling water (18-28℃)
|
4
|
Limit control of
solution concentration
|
The control system will
calculate the concentration of concentrated solution, crystallization and
safe temperatures based upon of measured actual operating data, and adjust
the operation conditions automatically, when the crystallization trends to
occur.
|
5
|
Automatic adjusting the
load
|
Cooling capacity of
chiller is automatically adjusted by regulating the heat source supply in
accordance with chilled water outlet temperature.
|
6
|
Automatic adjusting the
circulating flow of solution
|
Control system will
adjust the output frequency to the inverter to regulate the speed of solution
pump in accordance with the measurement of lever and pressure in the HP
generator, which will make the solution circulation to meet the requirements
of chiller operation.
|
7
|
Measurement and display of operation data in real time
|
Control system will
display the operation data, such as temperatures, pressures, levels on the
touch screen in real time by sensors installed, to make the operation
personnel to know the chiller more easily.
|
8
|
Safety protection
|
Control system will
protect the chiller from the dangerous operation, and take the appropriate
measures automatically.
|
9
|
Failure diagnosis
|
Determine the failure
conditions automatically on the basis of measured data, and take the
appropriate protecting measures .
|
10
|
Data storage
|
Control system will
store the operation data of last week, contents of last five failures, and
contents and operation data of last three failures.
|
11
|
Information storage
|
Control system stores
the information, such as working principle of chiller, guide of operation and
maintenance, which can be used by operational personnel, while operate the
touch screen.
|
12
|
Other extendible
functions
|
The control system reserves
extendible functions, such as the remote and concentrated control to meet the
requirements of customer.
|
4.2.2
Safety
Protection
Chiller will give alarm and stop operation, when it
surpasses the set values. The safety protection items and set values are
indicated in Table 4-2.
Table 4-2 Safety protection data
7
|
Steam pressure
|
Nominal value +0.05MPa
|
|||
4.5℃
|
8
|
||||
Cooling water inlet temperature
|
18℃
|
9
|
|||
4
|
100℃
|
10
|
|||
65℃
|
11
|
||||
48℃
|
4.3 Control Panel
4.4 Control Flow Chart
Control flow chart describes the procedure of start and stop
of elements of chiller during its start/stop. Control process is shown in
Fig.4-4 “Control Flow Chart”.
4.5 Operation Method
4.5.1 General
Put the switch (single pole switch, normally at position ON),
which is installed in the upper portion of control panel, into the position
“ON”, lock the door of control panel, and put the switch at the lower portion
of control panel into the position “ON”. At this moment, the power supply is
connected. The signal “POWER” and “RUN” will display. Three seconds after the
display of WELCOME, on the screen will show the main menu as shown on the
Figure 4-5. Operator can start/stop the chiller as indicated by the menu. And
also to adjust the operating parameters, or to other control, and learn the
working principle, basic operation procedures and methods of maintenance.
Fig 4-5 Main Menu
WORKING PRINCIPLE OF
CHILLER Press this key, on the screen will show the flow chart of
chiller/heater for refrigeration and heating, and working principle for
refrigeration and heating also.
GUIDE FO OPERATION OF
CHILLER Press this key, on the screen will be show the more than 10 methods
of operation, such as sampling of refrigerant water, charge of solution,
inspection of chiller/heater for air-tightness.
HISTORY OF OPERATION
Press this key, on the screen will show the last three troubles and the
operation data during week.
CONTROL MODE
Press this key to select the mode of operation (Auto or Manual, the
chiller/heater cannot be changed to manual operation, while the unit is
operated under AUTO control).
MONITORING OF CHILLER Press this key, the screen
will show the figure of monitoring, which is dependent to the control mode.
Operator can operate the chiller/heater, solution, refrigerant and vacuum
pumps, and set the data, such as outlet temperature of chilled water. The
current information on the different parts of chiller/heater can be shown also.
SETTING OF PARAMETER Press
this key the adjustable data, such as the outlet temperature of chilled water
can be set, and diminish the deviation of displayed value and actual value of
operation data.
GUIDE TO MAINTENANCE
Press this key the screen will show the contents and methods of maintenance.
1) The screen protection function is provided,
which will stop display (blacken), if no operations of screen occurred during
1h. For this period the control function of chiller is maintained, and the
screen will continue work, if it is touched lightly.
2) The screen can be cleaned by soft wet rag,
no volatile solvent (such as benzene) can be used.
3) Internally set values and positions of
external toggle switches are fixed in the factory, and not allowed are changed
by customer.
4.5.2 Operation Mode and Control Selection
The Graph of Operation Mode selection can be selected by
pressing the Key OPERATION MODE
SELECTION of main menu, or pressing the Key MENU to have display the menu graph, then to select operation mode
by pressing the appropriate key. On the Graph of OPERATION MODE there are two operation modes (refrigeration and
heating), and two types of control (Auto and Manual). You can select the
operation mode and control type, and then to press the key “CONFIRMATION” to get the appropriate
chiller operation monitoring graph.
4.5.3 Data Setting
The Data setting graph can be selected by pressing the Key DATA SETTING of main menu on the touch
screen, or by pressing the Key MENU
on the right upper angle of screen. In later case, touch screen will display
menu graph, then to select Data setting graph by pressing the appropriate key,
when the screen is displaying other graph. There are two kinds of data can be
set, namely the regulating data setting and setting of deviation for displayed
data.
4.5.3.1Regulating
Data Setting
The regulating data should be changed, while the chiller
will be operated on the new conditions. Regulating data include set values for
chilled water outlet temperature, cooling water inlet temperature, pressure in
HP generator, and appropriate P I D values. P I D values should be set by
certified personnel.
Set values of data should be approved by
certified personnel from Shuangliang Service Company. The set values of
regulating data cannot be over its limiting value, and not too far from the
nominal operation conditions to prevent the chiller from abnormal operation.
There will be regulating data display graph by pressing the
key of setting of regulating data under the data setting graph. Pressing the
key of Password for data setting, input the correct password on numerical
keyboard, and press the key “Enter”
to have the graph of setting data. At this time, the data can be changed. The
graph remains unchanged, while the password is erroneous. The input deviation
will be cleaned by pressing the key CLR
on the numerical keyboard.
During changing the data, touch screen will display
numerical keyboard by pressing the push-button on the left side of data to be
changed. The data will be changed by input new values and pressing the key of
confirmation. The setting of data is finished by pressing the key “OFF” on the numerical keyboard.
4.5.3.2 Setting of
Deviation for Displayed Data
The deviation between the value measured by calibrated
standard instruments and displayed value on the touch screen can be removed by
changing the set deviation of displayed data. For example, the value of chilled
water outlet temperature measured by calibrated thermometer is 7℃, and displayed value of this
temperature is 6.5℃, then the deviation of displayed data should be
increased by 0.5℃ on the basis of set deviation. Changing of set
deviation is similar to that of changing of set value of operation data.
During changing the data, touch screen will display
numerical keyboard by pressing the push-button on the left side of data to be
changed. The data will be changed by input new values and pressing the key
CONFIRMATION. The data are set by pressing the key “OFF” on the numerical
keyboard.
4.5.3.3 solution pump
inverter frequency setting
Factory setting: lower limit for condensation temp 27℃
, inverter frequency 25HZ; upper limit 45℃, inverter frequency is
40Hz.
4.5.4 Operation of
Chiller
4.5.4.1 Start/stop of
Vacuum Pump
Vacuum pump can be started or stopped at any time. But
before attempting to start vacuum pump, it should be checked for oil level, and
operated in accordance of paragraph 6.8 of Chapter 6 Management of vacuum pump.
The graph of chiller monitoring is displayed by pressing the
key CHILLER MONITORING of main menu; or pressing key MENU on the upper right
angle to display the content of main menu, then pressing the key CHILLER
MONITORING to display the graph of chiller monitoring, when touch screen
displays other graph; or to display the graph of chiller monitoring after
selecting the operation conditions.
Purge is realized by pressing key VACUUM PUMP START to start
the vacuum pump, then open the lower purging valve and related purge valves.
Before shutdown of vacuum pump, close lower and upper purging valves then press
the key VACUUM PUMP STOP.
The lower purging valve of
vacuum pump should be closed, before the vacuum pump is to be stopped.
4.5.4.2
Start/Stop
of Solution and Refrigerant Pump
Solution and refrigerant pumps are started and stopped
automatically, when the automatic operation mode is selected. The only work to
be done by the operational personnel is to start and stop chiller in accordance
with the following procedure.
Solution and refrigerant pumps should be started or stopped
by the operational personnel in the following procedure manually, when the
manual control mode is selected:
The graph of chiller monitoring is displayed by pressing the
key CHILLER MONITORING of main menu; or pressing key MENU on the upper right
angle to display the content of main menu, then pressing the key CHILLER
MONITORING to display the graph of chiller monitoring, when touch screen
displays other graph; or to enter the operation monitoring by selecting the
mode of operation and control during the chiller shut down. Solution and
refrigerant pumps can be started or stopped by pressing the keys SOLUTION PUMP
START, REFRIGERANT PUMP START, or SOLUTION PUMP STOP, REFRIGERANT PUMP STOP.
1) Before startup of solution pump, it is
essential to ensure that solution has been charged.
2) Prior to startup of refrigerant pump,
strong solution concentration shown on touch screen should be ensured above 56%
and chilled water system is to be checked to protect heat transfer tubes from
freezing.
3)
During
manual control the solution pump is not allowed to be operated by manually
operating inverter, and should be controlled by the control system according to
the solution level and temperature.
4.5.4.3
Start/Stop
of Chiller
The chiller monitoring graph is displayed by the operation
mode selection and data setting in 4.5.2 and 4.5.3. Graph of trouble monitoring
will be displayed by pressing key TROUBLE MONITORING. The following operations
can be done, when the chiller trouble-free indicating red LED lights (except
failure of chilled water)
A.
Automatic
Control
In graph of CHILLER MONITORING press key SYSTEM START, and
press “CONFIRM” key shown in next graph, then operator can run chiller
following procedure displayed on touch screen to start chilled water pump,
cooling water pump. Until receives reflection of both starting signal of
chilled water and cooling water pump and chilled water flow signal, chiller is
not ready to be started, then should press key CONFIRM COMPLETED to start
chiller finally, in the meanwhile touch screen shows graph of CHILLER
MONITORING.
The chilled water pump is to
be started with its outlet valve closed. Then the outlet valve is opened step
by step to get the nominal flow rate. When chilled water pump and cooling water
pump are interlocked, their start and stop operation is controlled by chiller,
no need of personal operation.
Chiller is stopped by pressing the key SYSTEM STOP on the
graph of chiller operation monitoring. Following this operation, the chiller
will be operated with automatic dilution, after reach set terms chiller will
stop. Procedure of stopping cooling water pump and chilled water pump refers to
Fig 4-4 Control flow chart.
B.
Manual
Control
Under Manual Control mode, functions of interlocking with
external system and safety protection still are workable. Start chiller in the
same way adopted under Auto Control mode. Until receives reflection of both
starting signal of chilled water and cooling water pump and chilled water flow
signal, chiller is not ready to be started. Then should press key CONFIRM COMPLETED
to start chiller finally.
1) The solution pump is started and solution circulation is
controlled automatically by pressing the key SOLUTION PUMP START. 2) Steam
adjusting valve will be opened by pressing the key STEAM ADJUSTING VALVE OPEN.
The opening of steam adjusting valve will be increased by 5% for every pressing
of the key. 3) Based on the requirements, Press REFRIGERANT PUMP START or
REFRIGERANT PUMP STOP to start or stop refrigerant pump. But refrigerant pump cannot
be started if strong solution concentration is less than 56%.
When stop chiller, press keys of REFRIGERANT PUMP STOP and
HOT WATER ADJUSTING VALVE CLOSE to stop refrigerant pump and close steam
adjusting valve (The manual steam regulating valve is closed manually). Then
stop fan of cooling tower, 3 minutes later close cooling water pump outlet
valve slowly and stop pump. When displayed concentration of solution is lower
than 56%, press key SYSTEM STOP to stop solution pump, then close chilled water
pump outlet valve slowly and stop pump.
4.5.4.4
Operation
Monitoring of Chiller
The operation conditions of parts and chiller and content of
trouble, if any, can be displayed to the operational personnel by the graph of
chiller operation monitoring.
4.5.4.5
Trouble
Shooting
The chiller will give alarm and stop operation
automatically, when trouble occurs. The alarm bell will be silent, and trouble
content graph will be displayed upon pressing the key TROUBLE MONITORING by the
operational personnel. The content of trouble will be shown (by the red light
before the trouble). The cause of this trouble and method of shooting will be
given by pressing the key TROUBLE FUNCTION. The TROUBLE MONITORING will be
returned, when the return key is pressed.
Chapter 5 COMMISSIONING OF CHILLER
5.1 Preparing to Commissioning
Chiller shall be commissioned by Shuangliang authorized engineer
with the assistance of customer
5.1.1 Inspection of
Exteriors and Installation Engineering
1.Check
chiller for absence of severe vibration and shock, painting, cracking of
hermetically sealed pumps, damage and deformation of control panel, inverter, instrument,
valves and cables, check chiller raining damage or exposition to the open air
for long time. Recover chiller, if there are damages or deviations.
2.Check
the installation, which should meet the requirements.
5.1.2 Inspection of
External Conditions
5.1.2.1 Inspection of
Chilled and Cooling Water Piping
1)
Check piping system for cleanness, cooling
tower, pond and outlet connections for foreign matters.
2)
Check piping system for drain and vent at the
lowest and highest points of piping respectively.
3)
Check the system for filter.
4)
Check the piping system again the drawing. Check
the piping for the correct direction and position, piping system for its
hanging, supporting to avoid the transmission of load to the end covers of
water boxes.
5)
Check water systems for leakage, pumps and
piping for vibration, flow rate to meet the requirements. Install water
treatment means, if poor water quality.
6)
Check the piping system for thermometers,
thermostats, flow switches, temperature sensors, and pressure gages for their correct
installation positions.
7)
Check pumps for: a. Absence slackness of bolt
connections; b. adequate amount of lubricating oil and grease; c. leakage of
water through sealing. It should be not form continuous line of water; d. Check
the correct operation electric current; E. Check the pump for normal pressure,
noise and motor temperature.
8)
Check cooling tower for its correct type, water
flow and reasonable temperature difference; Check fan for its correct operation
and electric current.
5.1.2.2
Inspection
of Steam Piping
Inspect according to the provisions of 3.2.
5.1.2.3
Inspection
of Working Steam Condensate Piping
Inspect according
to the provisions of 3.3.
Check the manual
stop valve for opening, when it is installed in the steam condensate piping. It
is kept opened during operation.
5.1.3 Inspection of
Vacuum Pump
1)
Check vacuum pump oil for its correct type;
check vacuum pump oil for its appearance, oil will be emulsified, if it
contains water.
2)
Check vacuum pump for its correct rotation.
Ensure the low purge valve of vacuum pump is closed. Remove the plug from the
sampling and purge valve, and cover the valve opening by finger. Put the vacuum
pump into operation. The pump is operated in the correct direction, if air is
socked through the valve opening. Change the motor cable connections, if it is
rotated in the wrong direction.
5.1.4 Inspection of
Chiller for Air Tightness
The chiller has been tested for air tightness strictly
before shipping. However, leakage is likely to occur at some locations due to
vibration and impact during transportation handling, and installation. Chiller
should be rechecked for air tightness prior to starting the commissioning first
under vacuum, and then under pressure, if the former is not satisfactory. The
inspection of air tightness is repeated to get the satisfactory results.
5.1.4.1 Leakage
Detection under Vacuum
1) Close all valves, which are exposed to atmosphere. The chiller is evacuated by vacuum pump to a pressure below 30Pa, if it is no tested in factory. Stop the vacuum pump, record local ambient temperature t1 and read the absolute pressure p1 by McLeod gage. Record ambient temperature t2 and absolute pressure p2 in chiller after 24h. Calculate the pressure increase ( ) in the chiller by the following formula, and shall not exceed 5Pa:
2) Chiller, which had
been tested in the factory, shall be tested for air-tightness by the air
bubbles, that a rubber or plastic hose shall be connected with the discharge
opening of vacuum pump at one end, and inserted about 50mm clean water into the
vacuum oil in a vessel at the another end. Close sampling valve, start vacuum
pump then close ballast valve of vacuum pump, and count the number of bubbles
per minute from water when numbers of bubbles become stable. Open upper purge
valve of vacuum pump and lower purge valve of vacuum pump and observe the
bubble numbers. If the number is big, chiller needs to be made vacuum. Count
again when bubble numbers become less. And if the bubbles number difference
when purging valve open and close are less than 3, close upper and lower purging
valves and stop vacuum pump. If it cannot reach the normal numbers after 2
hours and keeps in a rather big number, the chiller should be checked for
leakage by positive nitrogen gas pressure.
5.1.4.2 Leakage
Detection under Pressure
The chiller is charged with nitrogen (for LiBr solution charged
chiller only nitrogen is used) to the pressure of 0.08MPa or dry oil free
compressed air, and possible locations of leakage for welds, valves, flange
seals, etc is covered by soap solution. Leakage takes place while bubbling.
Then vent nitrogen from chiller and repair by welding. After that, the chiller
is rechecked under vacuum as mentioned earlier.
Gas is charged and vented normally by refrigerant sampling
valve (refrigerant is bypassed, then gas charged), or other valves, which
communicate with atmosphere, if chiller is not filled with solution and
refrigerant.
Before filling gas the purge valve of condenser and upper purge valve
of vacuum pump shall be opened.
5.1.5 Inspection of
Control Elements and Electric Equipment
During transportation and installation of chiller the
control elements and electric equipment is easy to be damaged. So after
installation, the chiller is to be checked for its completeness by the
personnel of Shuangliang Service Co.
1)
Inspection
of Field Wiring
Check the power and interlocking wiring of power source and
its equipment (such as cooling tower, pumps, and etc.)
2)
Inspection
of Chiller Control
Inspect the control panel for its intactness, and correct
wiring, data setting and installation of sensors and flow switch.
5.1.6 Charging of
Solution
LiBr solution is supplied with
(0.20±0.05)% of lithium chromate
or(0.015±0.005)%
of lithium molybdate as corrosion inhibitor. pH value for LiBr solution mixed
with lithium chromate has been adjusted to 9-10.5, and concentration of (50±0.5)%.
Alkalinity for LiBr solution mixed with lithium molybdenum has been adjusted to
0.01N~0.2N, and concentration of (50±0.5)%. These data should be reconfirmed before
their charging into the chiller.
Solution is charged under negative pressure through solution
charging valve at the discharge side of solution pump. Before solution is
charged, the weak solution regulating valve and intermediate solution valve is
opened. Evacuate the chiller down to absolute pressure in the chiller is lower
than 100 Pa (or to the water vapor saturation pressure, equivalent to the
ambient temperature, if the chiller is charged with solution or water). Then,
as shown in Fig. 5-1, connect the vacuum or reinforced rubber hose to the
connection of solution charging valve with vacuum grease from one end, and hose
is filled with solution. Emerge the hose into a vessel with solution of 0.6m3
from another end. Open the solution charging valve and solution will be suck
into the chiller. Keep the end of hose under the solution surface in the vessel
constantly, and adjust the valve opening to a normal flow rate of solution.
Solution is charged in two portions. First charge solution
about half the required amount. Then the solution-charging valve is closed and
operate the solution pump to transfer solution into the generator. Stop the
solution pump, when the solution pump makes noise of evacuation. Then charge
the rest solution.
After charging of solution, start the vacuum pump to purge
the chiller.
Solution is charged manually. But solution pump cannot be controlled by
the inverter under the manual mode, but controlled by the control system.
Before starting the solution pump, the vacuum pump shall be checked for correct
rotation.
5.1.7 Charging of
Ethanol
Ethanol with content of about 0.3% (weight) of solution is
charged in the similar manner as solution.
5.2 Commissioning of Chiller
The
chiller should be commissioned by Shuangliang authorized engineers on manual mode.
Site commissioning should be according to the actual
situation, adjust LiBr solution quantity of cycling and refrigerant water
quantity. Check and adjust auto control and safety protection instrument, after
those series adjustments, chiller can run with high efficiency in operating
state.
Commissioning
Procedure
1)
Switch on air breaker on chiller control panel
and check control system power supply.
2)
Press button of “Control Mode” and choose
“Manual Control” and then press “Chiller monitoring” to enter operation
monitoring graph.
3)
Press the button of “Start vacuum pump” to start
vacuum pump and confirm its attainable limiting vacuum. Then Open lower and
upper purging valves to evacuate chiller.
4)
Start chilled water pump and open chilled water
pump outlet valve slowly. Then adjust chilled water flowrate (or pressure
difference) to its rated value and reconfirm the function of chilled water
failure protection.
5)
Start cooling water pump and open cooling water
pump outlet valve slowly. Then adjust cooling water flowrate (or pressure
difference) to its rated value
6)
Open the manual valve in steam inlet pipe and
drain all the condensate water .
7)
Press buttons of “Start System”, “Confirm” and
“Reconfirm” to start system. Control mode is “Manual”.
8)
Press button of “Start solution pump” to start
solution pump when the pump will run at 27Hz.observe after 10minutes whether
the solution level in generator is stabilized at the middle of sightglass. If
yes, there is no need to change inverter setting .if the solution level merges
the sightglass, the minimum frequency of the inverter shall be reduced. Each
time reduce 1HZ till the solution level is stabilized in the middle of the
sightglass.
9)
Press button of “Steam adjusting valve open”.
The valve will be opened by 5% for each pressing of the key. The openness of
the valve shall be increased slowly .When closing the valve, press button of
“Steam adjusting valve close” and the valve will be closed by 5% for each
pressing of the key.
10)
When the concentration of strong solution
reaches 56%, press the button of “Start refrigerant pump”, slowly adjust the
refrigerant valve.
11)
When chiller is at full load, Observe whether
the liquid level in generator is at 1/3~1/2 of the sightglass.
If not, adjust the inverter frequency setting if necessary.
12)
Check if refrigerant is contaminated or not,
.method sees Chapter 6.5 “refrigerant water management”. When chiller reach
rated cooling capacity and refrigerant water is not contaminated, and the
concentration difference between weak solution and strong solution is around
5%, commissioning work complete.
13)
Chiller stop. Press “modulating valve close”
button and “stop refrigerant pump” button. Then close steam inlet manual valve,
stop cooling tower fan. After 3minutes slowly close cooling water exit valve
and stop pump. When the concentration is shown lower than 56%, press “system
stop” button or “solution pump stop” button, then close chilled water outlet
valve and stop chilled water pump. Finally switch off the power supply for
control box and system.
Caution:
1)
There
shall be enough refrigerant water in the refrigerant tank otherwise the pump
will get damaged due to empty rotation. If the pump empty rotation happens
frequently, SL engineer shall help to find out the reason .With his permission,
distilled water may be added inside.
2)
In
case ambient temperature is lower than 20℃
and chiller stop over 8 hours, all the refrigerant water shall be bypassed from
evaporator to absorber.
Chapter 6 OPERATION OF CHILLER
6.1 Safety Protection Rules
1.
In the machine room, the “Operation Procedure of
Steam Operated single effect Lithium Bromide Absorption chiller”, issued by
Shuangliang Co., should be hung.
2.
For machine room the strict rules of management
and shift relief had to be formulated. Unauthorized person is not permitted
enter the room, and touch the safety devices. The chiller cannot be operated
independently by the personnel not trained by the Shuangliang Co.
3.
The steam operated single effect chiller with
steam pressure greater than or equal to 0.1MPa, the HP generator belongs to the
first class pressure vessel, and should be operated, maintained and checked
periodically in accordance with the “Rules of safe operation and supervisory of
pressure vessels” and other provisions.
4.
The chiller should be confirmed to be without
any leakage, which would influence the life cycle of chiller. The chiller is
considered with leakage, if its working under cooling mode is dependent on the
running of vacuum pump. Then the chiller should be checked for air tightness
with nitrogen charged. The chiller should be maintained with periodically
change of sealing elements by the ones of same type or same material and with
correct exchange method.
5.
The rust spots, especially spots on the welding
connections, should be cleaned and painted, if the rust occurs, otherwise the
rust will cause the leakage. The machine room should be protected from
explosion by keeping the electric elements far from the paint, and the chiller
is not working, when it is painted. No corrosive, explosive and poisonous gas
is permitted in the machine room.
6.
The safety devices are not allowed to be set
over the permitted limits. The chiller cannot be started in case of potential
trouble with the safety devices. The chiller should be operated without any
trouble.
7.
The chiller is shipped from manufacturer with
the chilled water flow for the flow switch set to the minimum allowed value. It
is strictly forbidden to decrease the set value of flow switch. It is strictly
forbidden to start the chiller with the chilled water flow switch in trouble.
The chiller is forbidden to operate with the vibrating piping.
8.
It is not allowed to first shutdown the chilled
water pump, and then the cooling water pump.
9.
The chilled water pump and air conditioning
units should be stop only when the chiller is in standstill.
10.Only
the specified power supply should be used, and prohibit to touch the switch,
wire and elements in the control box to avoid electric shock. The power should
be cut off after the chiller stops its operation.
11.Electric
motors and elements cannot be get wet to keep them running safely.
12.The
operation of chiller is forbidden with control panel opened.
13.The
operation of chiller is protected from scald the operational personnel by
keeping them from touching the high temperature parts, such as the HP
generator, heat exchanger and its associated piping.
14.The
chiller should be checked and maintained strictly with the provisions of
chapter 8 “Maintenance and Service”
15.Lithium
bromide solution is not poisonous, but irritant when it is mixed with octanol.
The machine room should be kept with good ventilation. The place dripped with
solution should be washed immediately.
16.The
machine room should be kept with temperature in the limits of 5-40℃,
and relative humidity less than 90%.
17.Before
operation of vacuum pump, the oil trap should be drained to be empty by opening
the screw at the bottom of oil trap.
18.The
battery for PLC and touch screen should be changed periodically (once for 2
years). Change of battery should be finished in 5 minutes. For PLC, the battery
should be changed in the interval of 7 days of total standstill conditions of
PCL to avoid loss of program, if the ERR indicator on CPU is light, but the
chiller can be operated further. For touch screen, the battery should be
changed in the interval of 5 days of total standstill conditions of touch
screen to avoid loss of program, if the POWER light turns red, but the chiller
can be operated further.
6.2 Procedure of Operation
6.2.1 Procedure of Starting
1.
The air breaker in the control panel is closed,
and on the graph of “TROUBLE MONITORING” the NO TROUBLE indicator lights
(except the trouble of failure of chilled water), and the graph can be switched
to the “CHILLER MONITORING”.
2.
The chilled water pump is started when the valve
on the chilled water pump outlet is closed, and then to open the valve slowly
to adjust the flow or pressure drop to the nominal value.
3.
The cooling water pump is started when the valve
on the cooling water pump outlet is closed, and then to open the valve slowly
to adjust the flow or pressure drop to the nominal value.
4.
Open the steam valve, when the condensate
drained.
5.
Press the key “SYSTEM START”, then the key
“CONFIRMATION”, and finally the key “RECONFIRMATION” on the “CHILLER
MONITORING”, to put the chiller into the operation condition.
6.
Start the fan of cooling tower, and adjust the
cooling water flow to control the cooling water outlet temperature in the
limits of 36-38℃.
7.
Check the chiller operation periodically, and
take records every 2h.
To decrease the flow rate of cooling water in case low cooling water
temperature or running at low load conditions.
6.2.2
Procedure
of shutdown
1.
Close the steam inlet valve, and press the key
“SYSTEM STOP”, and chiller will be put into operation of dilution.
2.
Stop refrigerant water pump automatically when
detected concentration reaches 58%.
3.
When detected concentration reaches 56%,
automatically stop solution pump with time-log of 5 minutes.
4.
Cut the power supply from the control panel.
1.
All
refrigerant water should be bypassed from evaporator to the absorber during
shutdown, when the ambient temperature is less than 20℃,
and the chiller will stand longer than 8h.
2.
The
chiller is operated normally, when the safety device is checked periodically
and its normal working is guaranteed.
3.
Check
the chiller in accordance with the provisions of this technical manual.
6.3 Operation Observation and Inspection
In order to ensure the normal operation of chiller
constantly, observation of chiller is required during its operation. All
abnormalities should be debugged to avoid their potential risk occurs.
6.3.1
Observation
of solution level
1)
Observe the generator solution level constantly,
the over-high level and over low level which will harm to the chiller or even
damage. If the high level or low level happens constantly, please analyze the
reason.
2)
Check the solution pump and refrigerant pump is
idle sound, if yes, please analyze the reason and resolve it.
6.3.2
Observation
of chilled water outlet temperature
The chilled water outlet temperature should be checked
constantly. The cause should be fund, if the chilled water outlet temperature
rises, and it is not the influence of ambient conditions. The causes for poor
performance of chiller, such as the poor air tightness, the presence of non-condensable
gases, contaminated refrigerant water, crystallization of solution, less
surfactant additive (ethanol), scale formation on tubes, crack on the separator
plates in the water boxes and so on, should be closely analyzed.
6.3.3
Observation
of cooling water
The cooling water outlet temperature from the chiller should
be measured, and controlled in the limits of 38-40℃ by
means of starting or stop the fan for cooing tower, adjusting the bypass water
valve or water flow.
Cooling water should be carefully controlled for its
pressure and temperature difference in the inlet and outlet during operation.
Analyze the cause, if they changed greatly. If no significant changes for other
parameters, Chances are that heat transfer tubes have been scaled or blocked,
or cooling water cover clapboard gasket is broken etc.
6.3.4
Observation
of de-crystallization pipe
The de-crystallization pipe should be touched by the
operational personnel to test is it hot. In normal conditions, the piping end,
which is close to the absorber, can be touched by hand for a long time period.
If this end can be touched, but not for long time, which means there is some
solution flows through crystallization pipe, this cause would be checked. This
cause should be removed, if this is the mark of potential crystallization.
De-crystallizing measures should be taken, if it is very hot, and there is
potential crystallization on the strong solution side.
6.3.5
Inspection
of vacuum condition of chiller
The conditions should be analyzed, if the vacuum pump
evacuates non-condensable gas constantly. If the cause cannot be determined,
then the air tightness of chiller should be checked. The heat transfer tube may
be burst, or abnormal leakage occurs, if the pressure inside chiller is
increased considerably. In this case the chiller should be stopped immediately,
and chilled water and cooling water system should be checked, and the chilled
and cooling water system to be isolated from the chiller, and the air tightness
should be checked.
6.3.6
Inspection
of noise and amperage of running hermetically sealed pumps
Contact with Shuangliang Service Company to analyze the
cause, if abnormal noise and amperage is fund.
6.3.7
Adjusting
the deviation of displayed values
Check if there is deviation in the displayed value with the
actual value, and reset, if the deviation occurs.
6.3.8
Other
observations
1. Checking
vacuum pump for absence of emulsification and dirty.
2. Checking
the water pumps for absence of vibration and motors for overheating.
6.4 Purge Operation
Vacuum is vital for normal operation of chiller. The vacuum
(the quantity of non-condensable gas)
1. Upper purging valve 2.Lower purging valve
3. Sampling purging valve 4. Joint 1
5. Solenoid valve 1 6. Joint 2
7. Pressure sensor 1 8. Clamp
9. Solenoid valve 2 10.Vacumm pump
11. Gas cylinder connection pipe
12. Pressure sensor 2
13. Purging box 14. Auto purging
unit
15. Auto exhausting pipe 16. Oil trap
17. Oil drain plug 18.Tighten bolt
|
6.4.1
The
purge of new chiller or chiller after service and maintenance
The new chiller or chiller just after maintenance, which has
the internal pressure higher than the atmospheric pressure, should be vented to
the atmosphere through pressure sampling valve until the internal pressure is
equal to atmospheric. The chiller can be vented to atmosphere through other
valves, if there is no LiBr solution and water in it. Press VACUUM SYSTEM
button on chiller operation monitoring interface (as shown in Fig 6-2), press
MANUAL button on vacuum system interface (as shown in Fig 6-3), then press
START VACUUM PUMP button to purging vacuum. Details are shown as below,
1) Confirm that refrigerant
sampling valve, charging valve and strong solution sampling valve and other
valves which open into atmosphere are closed;2) Measure the limited purge capacity of
vacuum pump;3) Close sampling purge valve when meet the requirements, and fully
open upper purge valve of vacuum pump, then open slowly lower purge valve of
vacuum pump to purge, then fully open lower purge valve of vacuum pump to purge
when vacuum increases in chiller;4) If there is no solution in chiller, purge
pressure less than 100Pa in chiller, then close upper purge valve of vacuum
pump and lower valve of vacuum pump, and stop pump;5) If there is solution in chiller and purge
when chiller stops, a rubber or plastic hose shall be connected with exhaust
outlet of vacuum pump, and be inserted about 50mm into clean water in a open top vessel at another
end, close sampling valve, start vacuum pump then close ballast valve of vacuum
pump, and count the number of bubbles per minute from water when numbers of
bubbles become stable. Open upper purge valve of vacuum pump and lower purge
valve of vacuum pump and observe the bubble numbers. If the number is big, chiller
needs to make vacuum. Counting again when bubble numbers decrease. And if the bubble
number difference when purging valve open and close is less than 3, close
purging valves and stop vacuum pump. If chiller is running, close the
upper purging valve, and keep lower purging valve open; if chiller is stop,
close upper and lower purging valve.
Evacuate the chiller in the same manner, when the chiller is
purged not for the first time, and the vacuum is not as fair as normal.
Fig 6-2
Fig 6-3
6.4.2
The
purge of chiller during normal operation
During the operation of chiller, usually the automatic purge
unit is operating. Non-condensable gases will be purged and stored in the gas
cylinder. Control system will start vacuum pump according to gas cylinder
pressure automatically.
Press VACUUM SYSTEM button on chiller operation monitoring
interface, press AUTO button on vacuum system interface, close upper purging
valve and open lower purging valve. Control system will start vacuum pump and
open solenoid valves according to gas cylinder pressure automatically.
6.4.3
Trouble
Shooting
When problem happens about solenoid valves, close lower
purging valve. If solenoid valve 1 gets problem, loose joint 1 and 2, loose Oil
drain plug and Tighten bolt. After fixing, tight joint 1 and 2, and then tight Oil
drain plug and Tighten bolt. If solenoid valve 2 gets problem, loose the
joint which is connected with solenoid valve 2, after fixing, tight
the joint which is connected with solenoid valve 2.
During replacing solenoid valves, pay attention to the
direction of solenoid valves: arrow on solenoid 1 lead to up side, arrow on
solenoid 2 leads to Oil trap.
1.
During
purge operation, the lower and upper purge valves of vacuum pump shall be
opened slowly to protect the vacuum pump from spraying of oil or other failure
due to high evacuation rate.
2.
During purge operation the ballast valve for
vacuum pump should be opened, to avoid the emulsification of oil. Emulsified
white oil for vacuum pump should be changed in time.
3.
The
oil trap shall be thoroughly drained in predetermined period.
4.
If
solution is purged out from vacuum pump, solenoid valve shell, spool and O ring
should be washed ,and drain out the solution inside vacuum pump, wash vacuum
pump by clean water. Fill in new vacuum pump oil after cleaning.
6.5 Management of Refrigerant Water
During operation of chiller the LiBr solution droplets from
generator may be carried into the refrigerant water into the condenser or
evaporator by the refrigerant vapor. The refrigerant is contaminated, if it
contains LiBr. The chiller performance will be degraded with the contamination
of refrigerant water, and even had to be shutdown, when a lot of LiBr is
carried into the refrigerant. So the refrigerant density should be measured
periodically during operation of chiller. Refrigerant needs to be regenerated,
when it contaminated.
6.5.1 Sampling and
measuring the refrigerant water
Fig 6-2 Refrigerant sampling
1)
As shown in Fig. 6-2, the sampler is connected
to the sampling purge valve of purge system by vacuum rubber hose with the
connections covered by vacuum grease.
2)
Start vacuum pump and open the sampling purge
valve to evacuate the sampler for 1-3 min.
3)
Open the sampling valve for refrigerant water;
it will flow into the sampler.
4)
When appropriate quantity of refrigerant water
is taken, close the refrigerant sampling valve, then close the sampling purge
valve, and last stop the vacuum pump.
5)
Pour refrigerant water out of sampler into a
250mL cylinder, and measure the relative density of refrigerant water by
hydrometer with scale of 1.0-1.1.
Sampling and density measuring of refrigerant is preferred to use the
sampler and cylinder, which is not used for solution. Or the sampler and
cylinder had to be washed by clean water and no drop of water is left, when the
same sampler and cylinder is used for both refrigerant and solution. Sampled
refrigerant water should be placed separately.
6.5.2
Regeneration
of refrigerant water
The regeneration of refrigerant is carried out, when the
chiller is operating.
The refrigerant is to be regenerated, while it is
contaminated to density of 1.04g/ml. In this case, the chiller is operated with
part opening of bypass valve, i.e. the chiller is working for refrigeration and
regeneration of refrigerant water at the same time. The refrigerant bypass
valve is closed, while the cavitation of pump operation occurs. The process is
repeated to the normal density (1.002g/ml) of refrigerant water.
6.6 Management of Lithium Bromide Solution
Lithium bromide solution is corrosive to the construction
material of absorption chiller. For protection of chiller from corrosion, the
solution should be added with inhibitor, and controlled in the limits of 9-10.5
for its pH value. Contamination of solution with products of corrosion will
cause clogging of holes in distributor of absorber, and the lubricating and cooling
piping for the pumps, which will bring influence to the operation performance
and life cycle of absorption chiller. So the solution should be sampled and
measured periodically during the operation of chiller, and measures should be
taken to treat the solution in accordance with the results of measures. The
weak solution is sampled normally, and strong solution is sampled only when its
concentration is measured.
6.6.1
Sampling
of LiBr solution
Sampling of solution is carried out for weak and strong
solution in the similar way as for the refrigerant water. The solution sample
is taken from the charging valve at the discharge side of solution pump and the
sampling valve at the solution distribution box located at the bottom of shell
of chiller.
The weak solution sample is taken with the sealing plug
removed from the charging valve, and the Rubber hose connection, which is
delivered with the chiller, shall be installed. The connection shall be
removed, when the solution sample had been taken. Then the sealing plug shall
be installed to ensure the secondary sealing of valve.
6.6.2
Inspection
of LiBr solution
6.6.2.1
Inspection
of concentration of solution
Pour the solution in the 250mL cylinder. Measure the
concentration of solution by Baume hydrometer. The concentration of solution
can be determined by the graph (as per attached graph 2) with the measured
temperature and specific gravity, measured thermometer and hydrometer
respectively. Contact with Shuangliang Co., if solution concentration is
considerably different in comparison with the primary measured value.
6.6.2.2 Visual
inspection
The solution quality i.e. the foreign matter and consumption
of inhibitor can also be determined visually by the color of solution. The
visual inspection will be carried out after sampling by several hours. The
inspection results should be compared with the Table 6-1. The final results
shall be given by Shuangliang Service Co.
ITEM
|
M-Series LiBr
solution
|
C-Series LiBr
solution
|
||
Condition
|
Result
|
Condition
|
Result
|
|
COLOR
|
Gray
Black
|
Corrosion happened inhibitor
is consumed.
A lot of ferric
oxide is in the solution, and inhibitor consumed.
|
Light yellow
Colorless
Black
Green
|
A lot of inhibitor
is consumed.
Inhibitor consumed
considerably.
A lot of ferric
oxide is in the solution, and inhibitor consumed.
The corrosion
product copper oxide is in the solution
|
FLOATING MATTER
|
Very few
Rust scale
|
No problem
A lot of ferric
oxide
|
Very few
Rust scale
|
No problem
A lot of ferric
oxide
|
PRECIPITATE MATTER
|
Considerable
|
A lot of ferric
oxide
|
Considerable
|
A lot of ferric
oxide
|
Table 6-1 Visual control
6.6.3
pH
value
In order to control the corrosion in the chiller, the pH
value should be controlled in the limits of 9-10.5. The solution with pH value
not in these limits should be adjusted. The solution is shipped from factory
with the pH value in the above limits. With the operation of chiller, the pH
value will be increased. The pH value of solution should be checked
periodically by universal pH value test paper, and the results should be
recorded. If the pH value is too high, hydrobromic acid (HBr) may be added; if
it is too low, lithium hydroxide (LiOH) may be added.
The hydrobromic acid and lithium hydroxide shall be suitably
diluted prior to their additions to the chiller, and with appropriate rate.
They can be added in such a way: take a part of solution and pour it in a
vessel, then add the lithium hydroxide or hydrobromic acid, which is diluted
with 6 times of pure water. They should be mixed evenly.
The adjustment of pH value and
addition of this matter is rather complex, and is preferred under the
instruction of qualified engineer from Shuangliang Service Co.
6.6.4
Inhibitor
In order to control the corrosion of LiBr solution to the
chiller, the solution is added with inhibitor (Lithium Bromide (0.20±0.05) % or
Lithium Molybdate (0.015±0.005) %). In
the process of operation, especially in the beginning period, the inhibitor is
consumed rather rapidly. The Content of inhibitor in the solution should be
checked periodically by the special laboratory. The inhibitor content should be
kept in the set limits, when its content is out the limits.
The quantity of inhibitor should be calculated according to
the analysis of solution. Inhibitor should be added through refrigerant water
sampling valve during chiller is running, then fully open the refrigerant water
bypass valve to bypass all refrigerant water with inhibitor to solution. After
charging inhibitor, keep chiller running at least 3 hours to make sure inhibitor
is completely mixed with solution.
The addition of inhibitor is
rather complex, and is preferred under the instruction of qualified engineer
from Shuangliang Co.
6.6.5
Ethanol
Ethanol is used to improve the chiller performance. The
content of ethanol in the solution is 0.3%. Ethanol should be added, when the
content in the solution is lower than this value. The inadequate ethanol can be
determined by two ways: the one is the chiller performance is deteriorated; the
second is absence of irritant odor from the solution, or no irritant odor from
the vacuum pump discharge.
Ethanol is added in the similar way as for solution through
the charging valve or sampling valve under negative pressure.
6.6.6
Maintenance
of solution
Maintenance should be done if contents of solution changed. It
should be done based on analysis by Shuangliang
During maintenance of chiller, the solution
is transferred from chiller in following way: Firstly, the tank, in which the
solution is transferred, should be kept under high vacuum condition; Secondly,
during transferring the solution, the pressure difference is preferred be made
by introducing nitrogen. If in the worth case the air is used instead, then the
chiller should be purged immediately, when the transferring is finished.
6.6.7.1
Transfer of Solution to Chiller
1) Shown as Fig. 6-3, connect chiller with
solution stored tank by vacuum rubber hose. (Air in the hose should be
exhausted discharged)
The solution tank is charged by nitrogen
under the pressure of 0.02~0.04Mpa at gas inlet valve. Fig.6-3 Transfer of
Solution to between Chiller and Solution Stored Tank
3) Open the solution inlet/outlet valve in
the solution tank and the charging valve in chiller. The solution will flow
into the chiller automatically. The transfer of solution process has three
steps, which are just the same as 5.1.6.
4)After
finish charging solution, start up vacuum pump to purge promptly.
6.6.7.2 Solution
Transfer from Chiller to Solution Stored Tank
1) Shown as Fig.6-3,
connect chiller with solution tank by vacuum rubber hose. (Air in the hose
should be discharged)
2) Open the charging
valve of chiller and the solution inlet/outlet valve in the solution stored
tank, then start up solution pump to pump solution into solution stored tank
until the cavitation and stop.
3) If solution pump is
damaged and cannot start up, charge nitrogen with the pressure of 0.02~0.04 Mpa
to extrude the solution in chiller.
4) After finish
and pass the operation on detecting leakage, start up vacuum pump promptly to purge
vacuum. Detect leakage again if need.
6.7 Management of Water Quality
6.7.1 Management of
cooling water
During operation of chiller, cooling water outlet
temperature is preferred be kept in the limits of 38-40℃.
Cooling water temperature can be regulated by variation of speed of pump motor,
or by changing the opening of valve on the bypass pipe between the water inlet
and outlet of cooling tower.
During operation of chiller, cooling water should be sampled
and analyzed. The quality of cooling and makeup water should meet the
requirements of Table 6-2. Water should be treated, if it cannot meet the
requirements.
6.7.2
Management
of Chilled Water
Chilled water system can be opened or closed type. Soft
water is preferred, if closed system is adopted. For opened chilled water
system, it is managed as for the cooling water system.
Item
|
Unit
|
Makeup water
|
Cooling water
|
Tendency
|
||
Corrosion
|
Scaling
|
|||||
Basic
|
pH value(25℃)
|
6.0~8.0
|
6.5~8.0
|
○
|
○
|
|
electric conductivity(25℃)
|
<200
|
<800
|
○
|
○
|
||
chloric ion Cl-
|
mg Cl-/L
|
<50
|
<200
|
○
|
||
sulfuric acid radical ion
|
mg
/L
|
<50
|
<200
|
○
|
||
acid consumption rate(pH4.8)
|
mg CaCO3/L
|
<50
|
<100
|
○
|
||
Total hardness
|
mg CaCO3/L
|
<50
|
<200
|
○
|
||
Reference
|
Iron Fe
|
mg Fe/L
|
<0.3
|
<1.0
|
○
|
○
|
sulfuric ion S2-
|
mg S2-/L
|
undetectable
|
undetectable
|
○
|
||
ammoniac ion
|
mg
/L
|
<0.2
|
<1.0
|
○
|
||
silicon dioxide SiO2
|
mg SiO2/L
|
<30
|
<50
|
○
|
6.8 Operation of Vacuum Pump
Vacuum pump is vital equipment to keep the chiller under
vacuum condition. It is important to ensure the reliability of vacuum pump. The
vacuum pump should be maintained in the following manner. For more information,
see Operation manual of vacuum pump.
1. Before
the primary startup of vacuum pump, it should be test started for very short
period to determine whether the direction of rotation of pump meets the
indicated direction. This can be determined also by the gas, discharged from
the pump outlet. The checking of pump rotation can be done after the vacuum
pump oil is charged.
2. Vacuum
pump oil is charged or changed while the pump is shutdown to avoid the damage
of pump and splashing of oil.
3. The
vacuum pump should be start/stop repeatedly for short time to avoid damage the
pump by the loading from direct starting, if it is under long-term shutdown.
4. To
reduce the emulsification of oil, vacuum pump should be operated under opened
ballast valve.
5. For
long time evacuation and avoiding the oil emulsification, the vacuum pump
should be operated idly to warming up, then open the purge valve. Before
shutdown the vacuum pump, it also needs to work idly for a while to discharge
the water vapor, which mixed with the oil.
6. The
vacuum pump oil should be checked constantly for oil level and preventing the
oil emulsification. The oil level should in the middle of sight glass, and
drain the emulsified oil or water drops by screwing out the plug on the bottom
of oil box, if the oil is milk white. Then appropriate amount of oil should be
added. Oil should be changed and washed, if it is too dirty.
7. If
solution is purged out from vacuum pump, solenoid valve shell, spool and O ring
should be washed ,and drain out the solution inside vacuum pump, wash vacuum
pump by clean water. Fill in new vacuum pump oil after cleaning.
8. Vacuum
pump should be checked for its attainable limiting vacuum in the following. (1)
Remove the sealing plug from the purge valve, and connect Macleod gauge to the
sampling purge valve with vacuum grease by means of rubber hose. (2) Take off
the sealing plate from the oil trap and rubber hose connection from vacuum
pump, connect the vacuum pump with oil trap. (3) Run vacuum pump for 3 min,
then open slowly sampling purge valve and measure the pressure by Macleod
gauge. Vacuum pump is satisfactory, if the pressure is less than 30 Pa. Otherwise, the
vacuum pump shall be checked till satisfactory results are obtained.
9. The
vacuum pump should be removed from the chiller while it is stop running for a
long period as follows: 1) Close the upper and lower purging valves of vacuum
pump;2) Take off the sealing ring (or rubber tube) of at the end of sampling
purging valve, and open the sampling purging valve;3) Remove the metallic hose
connected between the oil trap and vacuum pump;4) Install the sealing plate
shipped with the chiller at the lower part of oil trap to stop the function of
trap;5)Install the rubber hose connection piece shipped with the chiller at the
suction of vacuum pump, and connect the rubber hose DN10 covered by vacuum
grease with the sampling purging valve; 6) Start the vacuum pump to evacuate
the non-condensable gas from the trap, and close the sampling purging valve and
stop the vacuum pump after 10 min of its running; 7) Remove the rubber hose
from the purging valve and plug it.
Note:Please kindly note item 8 and
9 should be operated by Shuangliang service engineers.
6.9 Description of Operation of Valves
6.9.1
Method
of Operation The Valve
Here followed the methods of opening and closing the valve,
and changing the sealing ring, valve plug and others. The working principle and
description of construction of valve are included in the “Operation Instruction
of Welded Special Valves”. For the application of torque wrench, see its
operation.
1) Method of Opening
The Valve
1) Remove the upper hood, check and tighten the press-cup
(turn the press-cup in anti-clockwise for tightening).
1)Turn
the valve stem in anti-clockwise by wrench to open the valve.
2)Install
the press-cup on place with the Loctite at the threads, and tighten the
hood.
2) Method of Closing
The Valve
1)
Remove the upper hood.
2)
Adjust the setting value of torque wrench to the
permitted torque for the valve.
3)
Turn the valve stem in clockwise by wrench to
close the valve.
4)
Check and tighten the press-cup (turn the
press-cup in anti-clockwise for tightening).
5)
Install the press-cup on place with the Loctite
at the threads, and tighten the hood.
Note:
1. For the purging,
charging, refrigerant probe, concentrated solution probe and pressure measuring
valves, which led to the atmosphere, block is inserted into the valve. Operate
these valves after taking out the block, and insert the block on the Loctite
after operation.
2. For probing the weak
solution through the charging valve, after the block had been taken away, the
valve outlet should be connected with intermediate part supplied with the
chiller, and then operate. After the probe had been taken, remove the
intermediate part, and install the block on the Loctite.
3) Method of Changing The Sealing Ring or Valve
Plug
1)
Remove the upper hood.
2)
Turn clockwise the press-cup to remove it.
(Loosen the fitting screw, if it is provided.)
3)
Take out the valve stem from the valve body, and
change the O-ring or under part of stem (with valve plug).
4)
Install the valve stem into the valve body with
the O-rings covered with vacuum grease.
5)
Tighten the press-cup anti-clockwise, and turn
the valve stem by torque wrench to adjust the valve by closing and opening it.
6)
Install the press-cup on place with the Loctite
at the threads, and tighten the hood.
3)Troubleshootings
No
|
Trouble
|
Cause
|
Measure
|
1
|
The valve stem cannot be turned.
|
Seizing of upper driving thread of valve stem
|
Remove press-cup, take out valve stem, repair the driving
thread. Change the valve stem, if the thread cannot be repaired.
|
2
|
Leaking of sealing
|
Scratch at the surface of valve plug
|
Change the under part of valve stem (with the valve plug).
|
Damage at the hole surface of scratch at the sealing
surface.
|
Change the valve.
|
||
3
|
Leaking of O-ring
|
Damage or aging of O-ring
|
Change O-ring.
|
The FDN 100 type torque wrench is used with overall length
of 380mm, torque limits of 20-100Nm, torque tolerance of ±4%.
The overall view of torque wrench is shown on the Fig.6-4.
Fig. 6-4 Torque wrench
1)
Allowable torque limits for the valve stem
Allowable torque limits for the valve stem is 40Nm for type
DN10/I; 40Nm for type DN10/II; and 70Nm for type DN25.
2)
Preset torque
Turn the handle, the dial disk will be revolved accordingly,
stop at the place, where the required torque is at the red division on the dial
disk. Then fix the torque by turning the rear cover in the direction of arrow
to stop.
3)
Force applying
Apply the wrench with preset torque to the valve stem, turn
it in the direction “¯” smoothly. The valve is closed, when “click” sound is
taken place, or the hand feeling became different than before. The operation is
finished at this moment. Stop applying force, and keep the original position of
wrench.
4)
Storing
After the operation, the torque setting should be restored
to the minimum value for store the wrench.
5)
Note:
1.The
wrench can be applied only in the direction of “¯”.
2.Never
use the wrench over the allowable torque.
3.Never
disassemble the wrench by yourself.
6.10 Safety guidance for operation
1)
Control system of chiller shall be interlocked
with that of chilled water pump and cooling water pump to be started and
stopped.
2)
When design and install external chilled water and
cooling water pipelines, the valve should be installed before chiller inlet and
outlet, and one bypass pipe between valve before chiller inlet and valve after
chiller outlet, parallel to chiller with valve, when clean pipeline after
finished installation of all pipe system, close valves of chiller inlet/outlet,
open valve of bypass pipe, make clean water flow through bypass pipe. After
finish cleaning, drain out water, close valve of bypass pipe, open valves of
chiller inlet/outlet.
3)
The chiller and all pump inlet should install
with filter following the operation manual, otherwise, if dirty in water enter
into chiller and jam the heat exchanger, which may degrade chiller’s
performance, or even result in tubes being frost cracked or other severe
damage.
4)
Before installation, the transportation rack
shall be removed, and then put the chiller on foundation. If the rack did not
removed, it should cut off the angle iron or wedge weld on rack to fix both
ends of heat exchanger. For some models, one angle of heat exchanger is welded
on rack, the other end is fixed with evaporator-absorber body shell, which only
this steel angle should removed.
5)
When charge or transfer solution, it shall do
best to reduce loss of solution, after operation, it shall flush solution sprayed
on ground and chiller body by water to clean them. For area of chiller body
paint has been damaged, it should be painted immediately.
Chapter 7 TROUBLESHOOTING
7.1 Shutdown of Chiller/heater due to Troubles
During operation of chiller/heater, control system will
check the running conditions of different parts of chiller to judge if chiller
is running in normal conditions. The control system will automatically solve
the 3 type troubles shown below. For troubleshooting process, see Fig.4-4.
1) If any below abnormal phenomena occurs, chiller will be
unloaded firstly. If chiller system still does not turn well after 10-minute
unloading, control system will alarm immediately and automatic shut down
chiller after turning into dilution operation.
(1) High
condenser temperature;
(2) Low
cooling water temperature;
(3) High
de-crystallization pipe temperature;
(4) High
steam pressure;
(5) High
generator solution temperature
2) When overcurrent of refrigerant water pump occurs,
chiller will alarm immediately and shut down after turning into dilution
operation. When overcurrent of vacuum pump occurs, chiller will alarm
immediately. When cylinder gas pressure reaches set valve, a graph will appear
automatically on the graph of operation monitoring on the touch screen showing
“High pressure in chiller auto-purging unit, please start vacuum pump”. The
operator may start purge according to methods introduced in “6.4 Purge
Operation”.
3) When any following severe trouble occurs, chiller will
alarm instantly and shut down emergently.
(1)
Low chilled water temperature
(2)
Failure of chilled water
(3)
Low refrigerant water temperature;
(4)
Trouble in inverter;
During automatic shutdown of chiller/heater, the operator
should press key “TROUBLE MONITORING” on the graph of operation monitoring on
the touch screen to make the alarm silent and search for the cause of trouble
and its shooting. Operator should remove the cause of trouble immediately after
the trouble occurs, and then start again the chiller/heater.
7.2 Common Troubles and Their Shooting
7.2.1 Troubleshooting
for chiller
Table 7-1 Common Troubles and Their Shooting for Chiller
No
|
Trouble
|
Cause
|
Troubleshooting
|
1
|
No power display of control system.
|
1) No
power to control panel.
2) Switch
for control power supply is OFF
|
1) Check
main power supply and air breaker
2) Put
the control switch and main air breaker ON.
|
2
|
Poor vacuum
|
1) Leakage
in chiller.
2) Poor
performance of vacuum pump and trouble in purge system
|
1) Leak
test and remove the leakage.
2) Check
the vacuum pump for performance, and remove the trouble in the purge system.
|
3
|
Chilled water
temperature difference is less than nominal value.
|
1) Cooling
capacity is less than designed value.
2) Chilled
water flow is greater than nominal value.
3) Displayed
temperature is not correct.
|
1) See
No.6.
2) Reduce
the flow accordingly.
3) Correct
the display deviation.
|
4
|
High chilled water
outlet temperature
|
1) Cooling
capacity is less than designed value.
2) Too
great outside load.
3) Set
value is too high
|
1) See
No.6
2) Reduce
cooling load accordingly.
3) Set
the nominal value.
|
5
|
Contaminated
refrigerant water
|
1) High
solution cycling, high solution level.
2) Too
big solution charge
3) Low
cooling water temperature.
4) Too
high chilled water outlet temperature.
5) Too
much heat supply.
6) Poor
quality of solution.
|
1)
Adjust solution pump transformer frequency
properly.
2)
Drain part of solution.
3)
Regulate cooling water bypass valve; check
controller of cooling water inlet temperature.
4)
See No. 4
5)
Regulate heat supply.
6)
Sampling solution, and analyze, change
solution with more reliable quality.
|
6
|
Cooling capacity is lower than design value.(cooling mode)
|
1) Poor
vacuum
2) High
cooling water inlet temperature.
3) Less
cooling water flow.
4) Scale
or clogging of heat transfer tubes by foreign matter
5) Inadequate
heat supply.
6) Refrigerant
water contaminated.
7) Too
much or too less refrigerant water spraying quantity.
8) Too
much refrigerant water
9) Inadequate
Ethanol in solution.
10)
Less charge of solution.
11)
Solution cycling capacity is not enough.
12)
Low chilled water outlet temperature.
13)
The less cooling load from the user
|
1) See
No.2
2) Regulate
cooling water bypass valve; check the controller for cooling water inlet
temperature, check cooling tower and its fan.
3) Check
the valve opening and filter cleanness in the cooling water system, check the
cooling water pump.
4) Clean
heat transfer tubes.
5) Increase
heat supply.
6) Sampling
refrigerant water, and regenerate it, if density is greater than 1.04.
7) Close
refrigerant water bypass valve, little close or open the spray valve.
8) Drain
refrigerant water.
9) Add
ethanol.
10)
Charge appropriate amount of solution.
11)
Adjust solution pump transformer frequency to
ensure solution cycling meet the requirement.
12)
Cooling capacity will be reduced with the
reduction of chilled water outlet temperature. Set the nominal chilled water
outlet temperature.
13)
Normal situation during auto control
|
7
|
Crystallization during
startup
|
1) Air
leakage or a lot amount of non-condensable gas in chiller.
2) Too
low cooling water inlet temperature.
3) Overloaded.
|
1) Purge
chiller by vacuum pump.
2) Regulate
cooling water bypass valve to increase temperature. Check controller of
cooling water inlet temperature.
3) Increase
load slowly for startup.
|
8
|
Crystallization during
shutdown
|
Inadequate dilution
|
Check the set value for
dilution and actual situation.
|
9
|
Crystallization during
operation
|
1) Non-condensable
gas in chiller.
2) Too
less of solution cycling
3) Too
big heat supply.
|
1) Purge
chiller by vacuum pump.
2) Increase
solution pump inverter frequency.
3) Reduce
heat supply.
|
10
|
Sudden shutdown during
operation
|
1) Failure
of power supply or loss of phase line.
2) Safety
protection system works.
a. Abnormal
refrigerant pump.
b. Abnormal
solution pump
c. High
temperature of crystallization pipe.
d. High
temperature of generator solution
e. Failure
of chilled water
f. Failure
of cooling water.
g. Other
trouble
|
1) Check
power supply to restore it.
2) Remove
the cause of troubles, and restore the normal operation:
a. If
overload relay works, reposition and check motor temperature, amperage and
insulation.
b. As
per above item a.
c. Chiller
de-crystallization as per item 7、8、9.
d. See
No.11.
e. See
No.14
f. See
No.15.
g. Investigate
the trouble cause and remove it by pressing “Trouble Monitoring” at the
operation screen
|
11
|
High generator
temperature.
|
1) Poor
air tightness and air leakage
2) Heat
input is greater than nominal value.
3) High
cooling water temperature or low cooling water flow.
4) Severe
scale on the cooling waterside of heat transfer tubes.
5) Minor
cycling solution
|
1) Purge
the chiller by vacuum pump and remove the leakage.
2) Regulate
heat input.
3) Regulate
cooling water bypass valve, check cooling tower and fan, or regulate cooling
water flow.
4) Clean
heat transfer tubes.
5) Increase
solution pump inverter frequency.
|
12
|
Cavitation of solution
pump
|
1) Inadequate
solution charged.
2) Crystallization.
|
1) Charge
solution.
2) De-crystallization.
|
13
|
Cavitation of
refrigerant pump
|
1) Inadequate
refrigerant water.
2) Low
refrigerant water temperature.
|
1) Add
refrigerant water.
2) Regulate
cooling water temperature or add refrigerant water.
|
14
|
Failure of chilled
water
|
1) Damaged
pump (or motor).
2) Inadequate
refrigerant water is added.
|
1) Repair
or startup standby pump.
2) Regulate
the cooling water temperature or add refrigerant water.
|
15
|
Failure of cooling
water
|
1) Same
as failure of chilled water.
2) Less
water is stored in the cooling tower.
|
1) Same
as for failure of chilled water.
2) Addition
of water storing capacity (for water collecting type cooling tower)
|
16
|
Abnormal decrease of
cooling capacity,
chiller pressure in
in the auto purge unit equal or above the
atmospheric pressure
|
The heat transfer tubes
leak or other parts leak abnormally.
|
Urgent measures should
be taken:
1) Cut
the power to shutdown the chiller.
2) Close
valve and stop the chilled and cooling water pumps.
3) Drain
the chiller.
4) Transfer
solution from chiller to tank; open the end covers to test the air tightness.
|
17
|
Decrease the vacuum
during shutdown period
|
Leakage
|
Test chiller for air
tightness.
|
18
|
Big variations of
values displayed on the touch screen(MMI2)
|
1) Poor
grounding.
2) Poor
sensors for temperature and etc.
3) Troubles
in touch screen.
|
1) Re-grounding.
2) Repair
or replace.
3) Replace.
|
19
|
Pump not operated.
|
1)
Pump motor overload protected.
2)
Troubles in the control circuit.
3)
Trouble in pump itself.
4)
Automatic protection of chiller works.
|
1) Find
the cause of overload and reset.
2) Check
the circuit.
3) Replace.
4) Find
the cause.
|
20
|
Buzzer not working.
|
1) Buzzer
damaged.
2) Fuse
blown.
|
1) Replace.
2) Replace.
|
7.2.2 Troubleshooting
for Electrical System
No
|
Trouble
|
Measure
|
1
|
No power supply for
control system
|
1. Check
the availability of power to the chiller.
2. Check
the air breaker of the control panel to the power at its input and output
sides.
3. Check
the single-pole switch of control loop for the control panel to the power at
its input and output sides.
4. Check
the power supply of control elements and apparatus in accordance with the
electrical principal circuit.
|
2
|
Trouble of control
elements and apparatus
|
1. Check
the normal input of control elements and apparatus. Check the normal
conditions of three phase and control power supplies for contactors. Check
the power supply and electrode circuit of level controller.
2. Check
the output of control elements and apparatus, for instance the output of
three-phase power supply, the output signals of high and low level output
signals of level controller.
3. Check
other control circuits, such as the control signal from the PLC to the
controllers, and etc.
4. Check
the function of elements and apparatus in accordance with their
instructions.
|
3
|
Trouble of touch screen
|
1.Check
the fixing of communication and power lines. Check the batteries of touch
panel (which should be changed every 2 years).
2.Check
the touch panel according to the troubleshooting instruction.
|
4
|
Trouble of PLC (ERROR
light up)
|
1.Check
the elements and apparatus step by step, including the PLC controller, the
power supply of controller, the input/output modules, base plate and PLC
batteries (for every two years).
2.Check
the PLC according to the operation instruction.
|
5
|
Trouble of external
measuring elements
|
1.Check
the fixing of connection lines and the situation of circuits (Connect new
lines from sensors to the control panel, and measure the output of sensors).
2.Check
the sensors (reconnect sensor to control box, and test sensor output is
normal or not.)
3.Check
the installation situation of sensors (such as the blockage of pressure
sensing hole for pressure sensors, and the damage of target plates of flow
switches).
|
6
|
Trouble of external
actuating elements
|
1.Check
the correct connection of circuits and control signal.
2.Check
the actuating elements according to the instruction.
|
7.3 Solution Crystallization and Its Treatment
7.3.1 Crystallization
during startup of chiller
Solution in the heat exchanger from the strong solution side
and in the generator may be crystallized as the low cooling temperature and
non-condensable gas exists in the chiller during its startup period. The
measures for de-crystallization are as follows:
1)
The de-crystallization measures are similar as
operation period see Chapter 7.3.2, if the crystallization of solution occurs
in the heat exchanger.
2)
When solution in generator is crystallized, then
the generator is supplied with minor heat from regulating valve to raise the
temperature of solution. For speeding up the de-crystallization, shell of
generator can be heated by steam from outside. The solution pump is started,
when the solution is de-crystallized, and the chiller can be put into
operation, when all solution in the chiller is even mixed.
3)
De-crystallize the generator at first, and then
the heat exchanger, if the generator and heat exchanger is crystallized in the
same time.
7.3.2
Crystallization
during Operation
The place prone to crystallize during chiller operation is
the strong solution side of heat exchanger and the strong solution outlet. Hot
de-crystallization pipe is the outstanding mark of solution crystallization.
But hot de-crystallization pipe also can be caused by the poor circulation rate
of solution. In general, if the hot de-crystallization pipe is caused by
crystallization, then the weak solution temperature at the outlet of heat
exchanger and the surface temperature of heat exchanger will go down. The
measures for de-crystallization are as follows:
1)
Change the control of chiller to manual mode,
and re-start the chiller by minor opening of steam adjusting valve.
2)
Stop the supply of cooling water to raise the
temperature of weak solution to about 60℃, but not above 70℃.Shut
the chilled water, when its outlet temperature is higher than inlet
temperature.
3)
Open the refrigerant bypass valve slowly to
bypass part of refrigerant to absorber to dilute the solution and not lower the
solution level in the absorber considerably. The solution will de-crystallize,
if the chiller is operated under such conditions continuously.
4)
Heat the crystallized parts by steam or
condensate, if they are difficult to be de-crystallized in short time.
5)
Put the chiller into operation, when it is
de-crystallized. The purge piping is also to be de-crystallized, if it had been
crystallized also.
6)
Find the cause of crystallization, and
appropriate measures are taken.
The chiller is normal, if the de-crystallization pipe is not
hot even under the full load of chiller.
7.3.3
Crystallization
during Shutdown
During shutdown the solution is crystallized, if it is not
adequately diluted during shutdown, or the cooling water temperature is low.
The solution pump cannot work for solution crystallization. It can be
de-crystallized by heating the pump casing and its inlet and outlet by steam to
run the pump. The caution should be taken to avoid the steam and its condensate
into the motor and its control means. No direct heating of motor is permitted.
7.4 Freezing of Refrigerant Water
Refrigerant water is frozen by low chilled water outlet
temperature or small flow, or failures in the safety protection means. So, the
safety protection should be inspected and calibrated periodically, or the
chilled water system should be checked and cleaned.
For de-freezing the refrigerant water, the cooling tower fan
should be stopped, the cooling water flow should be reduced, and the chiller is
put into operation in the normal manner. If the refrigerant water still is frozen,
then close the steam adjusting valve and solution pump.
7.5 Treatment of Emergency
7.5.1 Fire and earthquake
Cut the power supply, close all the valves, and take fire
protection measures.
7.5.2
Water
flooding
Remove the control panel and vacuum pump, and handle them to
safe place. All the hermetically sealed pumps, sensors and electric wires
should be covered by plastic films to be protected from water leakage.
7.5.3
Freezing
or cracking of heat transfer tubes (abrupt reducing of cooling capacity, and
abnormal rising of pressure in the chiller)
Stop chiller operation (stop immediately the refrigerant and
solution pumps), stop the chilled water and cooling water pumps after shutoff
their valves, and transfer the solution from chiller to the tank. Drain water
from the chiller, check the chiller for air tightness and change the broken
tubes by opening the end covers.
7.5.4
Chiller
shutdown due to failure
Analyze the reason of failure, and restart the chiller after
trouble shooting.
7.5.5
Failure
of Power Supply
When the power supply is failed, close the steam manual
valve, then close the valves at the discharge of cooling and chilled water
pumps and stop the pumps. If before the power failed, the sampling or purge
process was taken place, then the sampling valve and lower and upper purge
valves should be closed.
7.5.5.1
Treatment
for Short Period (less Than 1h) Failure of Power Supply
In general the solution is not tend to be crystallized, if
the power supplied is failed only for limited time, and solution remains hot.
In such case, the chiller can be put into operation, as the power supply
recovered.
1)
If the chilled and cooling water pumps had been
shut as the power failed, then these pumps are to be started by confirming that
the valves at their discharge had been closed. Then these valves opened and
adjusted to the flow required.
2)
Control the chiller manually, start the solution
and refrigerant pumps, and stop the chiller with dilution operation.
3)
Control the chiller automatically, start it in
the normal procedure.
4)
Check the refrigerant water for its density;
regenerate it, if its value is above 1.04.
7.5.5.2
Treatment
for Long Period (more than 1h) Failure of Power Supply
The crystallization of solution tends to occur, if the
chiller is shutdown for long period under high solution concentration. Operate
the chiller in the following ways, when the power recovered:
1)
Start the chiller manually for operation with
dilution as above mentioned for short shutdown.
2)
Operate the chiller under light load for 30 min
in trial manner, Stop the chiller for de-crystallization, if the temperature of
de-crystallization pipe is increased. If no crystallization occurs, then stop
the chiller, and re-start the chiller in automatic mode.
3)
Check the refrigerant water for its density
after de-crystallization; regenerate it, if its value is above 1.04.
7.6 Trouble of Vacuum pump
Troubles, causes and
their solutions are listed in Table 7-3.
Table 7-3 Normal troubles and their solutions for vacuum pump
No
|
Trouble
|
Cause
|
Solution
|
1
|
Low limit vacuum
|
1)
Oil cannot seals the discharge valve, noisy
discharge, as the oil level is low.
2)
Not correct type of oil is used.
3)
Oil emulsified.
4)
Leakage in the oil trap and its piping.
5)
Broken spring for revolving plate.
6)
Clogged oil holes lower the vacuum.
7)
Worn and torn the revolving plates and stator.
8)
Rubber components for suction pipe and ballast
valve not assembled correctly, broken or aged.
9)
Vacuum system, including piping, contaminated
severely.
|
1) Add
oil to the level in the limits of 5mm under middle line.
2) Change
to correct type vacuum pump oil.
3) Drain
the emulsified oil or water droplets from the drain plug on the bottom of oil
box, and add oil; change oil, if it is too dirty.
4) Check
for tightness, and remove leakage.
5) Change
to new spring.
6) Drain
the oil, remove the oil box, lose the press plate of oil nozzle, and withdraw
the oil nozzle and clean the oil holes. The components are cleaned, not using
gauze as far as possible.
7) Check,
repair and replace.
8) Adjust
and change.
9) Clean.
|
2
|
Oil spray
|
1) Too
high oil level.
2) No
oil or oil contaminated in oil separator.
3) Lost
or assembled not correctly the oil trapping plate.
|
1) Drain
oil to normal level.
2) Check,
clean and repair.
3) Check
and re-assemble.
|
3
|
Oil leakage
|
1) Broken
oil drain plug and gasket.
2) Broken
or assembled not correctly the gasket for oil box cover.
3) Deformed
thermally the plexiglass.
4) Lost
spring for oil seal.
5) Not
closed the ballast valve during shutdown of pump.
6) Oil
seal is worn due to error assembling.
|
1) Check
and replace.
2) Check,
adjust or replace.
3) Replace
and lower the oil temperature.
4) Check
and repair.
5) Close
it while shutdown the pump.
6) Reassemble
or replace.
|
4
|
Noise
|
1) Broken
the springs for revolving plates, and increased oil supply.
2) Worn
bearings.
3) Broken
parts.
|
1) Check
and replace.
2) Check,
adjust and replace, when it is necessary.
3) Check and replace.
|
5
|
Back flow of oil
|
1) Assembled
not correct or worn the oil seal in the pump cover.
2) Not
normal the surface of pump cover and stator.
3) Broken
the discharge valve plate
|
1) Replace.
2) Check
and repair.
3) Replace.
|
7.7 Troubles of Hermetically Sealed Pump
Troubles, causes and their solutions are listed as follows:
1)
Cavitation of pump
Cause and solution see Table 7-1.
2)
Bearings worn.
a.
The rotating parts of pump are not balanced
dynamically. Check and repair rotating parts.
b.
Cavitation in pump. Check and solve the problem.
c.
Foreign matters in solution. Re-generate
solution, check and clean filter.
d.
Pump flow is not in the appropriate limits, and
axial load is increased. Adjust the pump flow in the designed limits.
3)
Amperage of pump motor is increased.
a. The
internal resistance of pump is increased. Open and check the pump casing,
impeller and inducer. Remove the roughness of surface by sandpaper or other
mechanical means.
b. Abnormal
contact in bearings. Check and replace the bearing, sleeves and thrust plate.
Remove the cause for increased friction.
c. Abnormal
contact between the rotor and stator. Check the surface for abnormalities of
expansion deformation. Remove the cause for abnormal wear.
d. Poor
contact between the impeller and casing of pump. Check the assembly of pump
shaft and impeller and deflection of shaft. Adjust or replace the shaft, if it
is out of normal limits.
e. Foreign
matter in the pump casing. Disassemble the pump casing to remove the foreign
matter.
f. Reduced
motor insulation resistance and unbalance of resistance of coil for three
phases. Restore, or otherwise, replace the stator. Dry the motor slowly by
torch, if it is damped.
g. Motor
operates under absence of any phase current. Check the fixing of wire
connection of motor. Tighten it, if it is slack.
h. The
voltage and frequency of power supply is fluctuating. Check the power supply
line.
4)
Thermal relay protection is working frequently
a.
Pump motor overloaded and overheated. Check the
flow and temperature of working medium. Check and clean filter.
b.
Trouble in thermal relay. Check and replace the
thermal relay.
5)
Pump noisy and vibrated severely
a. Reversed
rotation of pump. Change the connection of leads to pump motor to correct
rotation direction.
b. Too
great or small pump flow. Check the pump operation to make the operation of
pump in the determined limits.
c. Cavitation
in pump. See Table 7-1.
d. Foreign
matter in pump. Check and remove foreign matter from pump.
e. Contact
of casing with the impeller or inducer. Check and repair.
f. The
fixing of bolts is slack. Check and repair pump.
g. Unbalanced
rotor of pump. Check and balance pump dynamically.
Chapter 8 MAINTENANCE OF CHILLER
The performance of chiller and its life cycle is dependent
not only upon the starting commissioning, but also the maintenance of chiller.
The maintenance of chiller is not so complex, but it had to be done vary
carefully. Chiller should be maintained periodically to operate it reliably,
prevent it from accidents and to increase its life. Violation of following
maintenance precautions causes the unnecessary loss.
1)
The
Hermetically Sealed Pump, stop valve, pipeline valve, motorized valve, auto
replacement etc components of chiller are for Shuangliang’s exclusive use.
Shuangliang exclusive spare are required for chiller maintenance and repair.
2)
Chiller
should be maintained by qualified maintenance personnel from Shuangliang
Service Co. Before the service is carried out, the power should be cut from the
control panel. It is forbidden to do the maintenance and repair under the power
is supplied to prevent the injuries and deaths of people from the electric
shock. During the handling and moving the chiller, the specialized instrument
should be used.
8.1 Periodical Inspection
8.1.1 Monthly
inspection
During operation of chiller, it is inspected monthly
following the Table 8-1.
Table 8-1 Items for monthly inspection
No
|
Group
|
Item
|
Content
|
1
|
Chilled water
|
pH value and inhibitor
in chilled water
|
Sampling and measuring
chilled water, adjust it, if it is out the limits.
|
2
|
Cooling water
|
Cooling water quality
|
Analyzing the water
quality, and treat it based upon the results.
|
3
|
External systems
|
1) Clean
filter.
2) Chilled
and cooling water pumps
3) Cooling
tower.
|
1)
Remove filters from external systems, and
clean them.
2)
Inspect, repair and change oil, tighten the
screw connections, especially the fundament bolts.
3)
Clean the tower from dirty, check fans for
slackness and drop of driving belts, correct them, if abnormality is found.
|
4
|
Control and safety protection elements
|
Reliability of working
|
Check the control and
safety protection elements for their working reliability. Check the
insulation between level sounding electrodes, and between the shell and
electrodes for short circuit.
|
8.1.2
Yearly
Inspection
Before the startup and shutdown in a yearly season, the
following inspections should be checked.
Table 8-2 Items for yearly inspection
No
|
Group
|
Item
|
Content
|
Time
|
1
|
Chiller
|
1) Clean
heat transfer tubes.
2) Inspect
chiller for air tightness
3) Painting
|
1) Open
the end covers of water boxes for chilled and cooling water, clean tubes and
end covers by brushes or chemical detergent, and replace the gaskets.
2) Check
the chiller for air tightness by the procedure illustrated in paragraph 5.1.4
of chapter 5.
3) Painting
parts or whole chiller based upon the rust conditions
|
1) After
shutdown.
2) Before
starting and after shutdown
3) After shutdown.
|
2
|
Solution
|
1) pH
value and concentration of additives in solution
2) Concentration
of solution
|
1) Sampling
and analyzing the solution, and adjust it based upon the results.
2) Measuring
the concentration after dilution operation, find cause and inform the
Shuangliang Service Co., if the abnormality is found.
|
Before starting
|
3
|
Refrigerant water
|
Refrigerant water
density
|
Sampling and measuring
the density of refrigerant, and regenerate it, when it is larger than 1.04.
|
Before starting
|
4
|
Pump
|
1) Hermetically
sealed pumps
2) Vacuum
pump
|
1) Check
the motor insulation, and measure its amperage. Inspect the bearings for
metal wear, repair or replace
2) Test
purging limit capacity of vacuum pump, if below standard, find cause and deal
with it.
3) Inspect
and clean vacuum pump.
|
Before starting
Before starting
After shutdown.
|
5
|
Electric parts
|
1)
Grounding of power supply
2)
Isolation resistance and electric strength
3)
Check fixing of wires on terminals.
4)
Electric control and protections
5)
Electric wires and cables.
6)
Flow switch
7)
Electric elements, such as sensors, inverters.
|
1) Check
power supply for grounding.
2) Check
motor and control panel for isolation resistance and electric strength.
3) Tighten
screws on terminals additionally.
4) Check
the electric control and protections for their set points and actual working,
check for wear of contacts and malfunction.
5) Check
and replace, if aged and corroded
6) Check
switch for its sensitivity, adjust it to normal function.
7) Check,
repair or replace based upon the actual results (for inverter, see its technical
manual )
|
Before starting
|
8.1.3
Other
periodical inspection
The following inspections and maintenance should be done for
the items listed in Table 8-3 according to the years of operation.
Table 8-3 Items for other periodical inspection
No
|
Item
|
Content
|
Time
|
1
|
External systems
|
Clean the piping from foreign matter thoroughly, and inspect
and repair the pumps, cooling towers, piping valves, electric distribution
lines, fuel and gas discharging system in the machine room.
|
Per 2 years
|
2
|
Hermetically sealed pump
|
1) Replace bearing
2) Capital repair and replace.
|
1) Per 15,000h.
2) Per 8-10 years.
|
3
|
Vacuum pump
|
Capital repair and replace.
|
Per 5-7 years.
|
4
|
Electric adjusting valve
|
Inspect, repair or replace
|
Per 6-8 years
|
5
|
Pressure gauge
|
Replace.
|
Per 3-4 years
|
6
|
Buzzer
|
Replace
|
Per 4 years
|
7
|
PLC battery
|
Replace (in less than 3 min)
|
Per 2 years
|
8
|
Relay and AC contactor
|
Replace
|
Per 8 years
|
9
|
Electric control panel
|
Replace
|
Per 20th year
|
10
|
Cut-off valve
|
Replace sealing ring.
|
Per 2-3 years
|
11
|
Vacuum relief valve
|
Replace sealing ring.
|
Per 2-3 years
|
8.2 Maintenance during Shutdown Period
8.2.1 Maintenance
during Short Shutdown
Short shutdown means the chiller is stopped for an interval
not longer than 1-2 weeks. Maintenance in this period is listed as follows:
1) The
solution in the chiller should be diluted fully. Refrigerant water from
evaporator should bypass into the absorber to weak solution and prevent
crystallization, when the ambient temperature is lower than 20℃, and chiller is stopped for more than 8h.
Operate the solution pump and stop refrigerant pump, connect the solution
charging valve at the discharge of solution pump and refrigerant sampling valve
together and open them, to prevent the refrigerant pump from freezing-up by
forcing the solution into refrigerant pump, when the ambient temperature is
lower than 5℃.
2) Maintain
the vacuum in chiller, operate vacuum pump, if absolute pressure in the chiller
is increased.
3) Check
the chiller for air tightness, if absolute pressure in the chiller is increased
too rapidly.
4) Drain
the chilled and cooling water systems (including chiller), if the local ambient
temperature will be lower than 0℃ in the interval of shutdown.
5) It
is forbidden to expose the chiller to atmosphere for long time during
inspection, replacing and repairing valves or pumps. The maintenance work
should be planed carefully, and the chiller is evacuated immediately after the
work finished.
8.2.2
Maintenance
during Long Shutdown
During long time shutdown, all refrigerant should bypass
into the absorber, and mixed with solution fully to prevent chiller from
crystallization and heat transfer tubes from freezing up. In order to protect
the refrigerant pump from freezing up during shutdown period, part of solution
should be bypassed into the refrigerant pump in the procedure shown in the
above first paragraph for “Maintenance during short shutdown”
During the long time shutdown the chiller should be under
supervision by special appointed personnel. The chiller should be checked for
air tightness, which is kept for good operation of chiller.
The solution can be left in the chiller, if it has good air
tightness and solution is clear. Solution is preferred be kept in special tank
to be settled, if it is turbid, and the chiller is rather severe corroded.
Solution may be treated outside the chiller, and then recharged into it.
Clean the chilled and cooling water systems (including the
chiller), and dry them during the long time shutdown in the following manner:
1)
From water systems drain up water, which flowing
during the operation of chiller.
2)
Clean and blow the internal surface of tubes and
pipes from rust and settlings (or by aid cleaning, if they cannot be removed by
usual cleaning).
3)
Drain the cleaned tubes and keep them dry (the
drainage piping is left opened)
8.3 Inspection of Air Tightness
Attention should be paid to the air tightness during
operation and shutdown. Inspect the chiller for air tightness, if abnormality
occurs. Inspection for air tightness is carried out for chiller under pressure
or under vacuum in the procedure shown in the paragraph 5.1.4 “Inspection of
chiller for air tightness” of chapter 5.
8.4 Inspection, Cleaning and Change of Heat Transfer Tubes
8.4.1
Inspection
of Heat Transfer Tubes
1) Inspection
of scale. Open end cover of water box to check, if there is scale and sludge in
the tubes. Scale is analyzed and measures should be taken, if it occurs in the
tubes.
2) Inspection
of air tightness Chiller is charged with nitrogen up to 0.08MPa. Tubes are
plugged from one side, and covered by a film of solution from another end. The
tube is broken, if there is bubble and broken at its end, or if the plug is
expanded off, when tubes are plugged from both sides. The broken tube can be
observed also, if bubble comes from the tube, when water funnel is installed
instead of end cover.
8.4.2
Cleaning
of Heat Transfer Tubes
Tubes are cleaned once a year based upon the scale and
sludge formation inside tubes.
1)
Mechanical cleaning. Mechanical cleaning is
effective to remove the sludge from the tubes. Remove the end cover, blow the
tubes with nitrogen or oil-less air under pressure of 0.7-0.8MPa. Then the
nylon brushes (not metal wire brushes) with rubber heads and air plugs are
inserted into the tubes, moved from one end of tube to another under high water
pressure for 2-3 times, and then dried by high pressure nitrogen or air, or
cotton balls. Cleaned tubes are protected by end covers.
2)
Chemical cleaning. Chemical cleaning is used to
remove scale, which contains salt with calcium, magnesium, and other hard
salts. Tubes are cleaned by chemical dosage, method and timed in accordance
with the content and thickness of scale formed.
Chemical cleaning
should be followed by qualified person of Shuangliang Service Co.
8.4.3
Leakage of chilled and cooling water through tubes will
dilute solution, deteriorate vacuum, increase corrosion and influence the
chiller performance. Leaky tubes should be withdrawn, changed by new ones, and then
expanded. It should be prevented to make longitudinal lines in the tube plate,
which will cause leakage in the connections.
8.5 Cleaning of Chiller
In addition to the LiBr solution regeneration, chiller is
cleaned when it is poor maintained, has corrosion products and foreign matter
in the solution, which will influence the chiller performance. Chiller is
cleaned by LiBr solution, distilled water or chemical solutions. But for
Shuangliang Co., chiller is cleaned solely by solution, and no distilled (or
softened) water or chemical solutions can be used. .
Cleaning of chiller by solution is similar to the operation
of chiller, but with minor heat supply by steam adjusting valve. Solution of
suitable temperature will wash off the dirt in the following manner:
1)
Start the chiller, and operate it for a period of time, then drain solution to
tank. Drained solution can be settled in solution tank, or filtered by two
tanks, if the settlement takes too long time.
2)
Start vacuum pump to evacuate the chiller up to high vacuum, charge it with
cleaned solution, and operate it. This process is repeated to have clear
solution drainage.
3)
After cleaning, the chiller is tested under pressure, especially the parts
disassembled.
4)
Solution should be regenerated after the chiller is washed by this solution,
and adjusted to the standard limits for inhibitor and content of foreign
matter. Chiller is purged continuously.
Comments
Post a Comment